Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct
Next week needs 14 people a day — 9 are booked.
Glass installation starts 7 Oct alongside joinery and painting. Shahid Iqbal (glass technician) is free from TS-26-016 after its snagging walk on 6 Oct; Ramesh Thapa has agreed.
Shahid Iqbal joins TS-26-014 on 7 Oct. With Elite Joinery and ProCoat, next week is planned at 14 people a day.
On site today
9
Own crew 7 of 7 · Elite Joinery 2
Subcontract work orders
AED126,000
4 work orders · 57,000 certified
Equipment at site
5
4 own · 1 rental due back 6 Oct
Own labour hours
1,247
To 30 Sep · AED 14,280 allocated
Own team
Today's GPS check-in · hours booked to this project in September| Person | Role on project | Today | Sep hours |
|---|---|---|---|
AK Arun Kumar Project Manager |
Leads 6 projects · client & costs | Site visit 2:00 PM | Overhead |
MR Site Foreman · TS-E004 |
Runs the site · daily report · petty cash | In 7:02 AM | 176 |
VR Vignesh Raman Site Engineer |
Drawings, RFIs, QA · shared with TS-26-019 | In 7:05 AM | 88 |
JJ Jomon Joseph Glass Technician |
Glass partitions & doors · drill set AST-TS-0021 | In 7:04 AM | 92 |
RD Ronald Dela Cruz Glass Technician |
Glass partitions · U-channels | In 6:58 AM | 108 |
KB Krishna Bahadur Carpenter |
Skirting, doors, joinery support | In 7:08 AM | 120 |
RH Rakib Hasan Helper |
Flooring & material handling | In 7:01 AM | 95 |
AK Abdul Kareem Helper · probation to 13 Mar 2027 |
Flooring & cleaning · joined 14 Sep | In 7:03 AM | 56 |
SI Shahid Iqbal Glass Technician · from TS-26-016 |
Glass installation, activity 7 | From 7 Oct | — |
| On site today: 7 of 7 | 735 |
Weekly manpower
People per day on site · W1 = week of 10 AugOwn crew steady at 7; subcontract labour fell from 8 to 3 a day. Pale bar = plan for next week (8 own + 6 subcontract).
Labour hours & cost
From GPS timesheets · cost code 07August512 h
September735 h
Avg per hour11.45
Allocated14,280
68%
AED 14,280 of the 21,000 own-labour budget used at 62% progress. Forecast 22,400 — see costs.
Client side
Who signs, who checks- KMApproverKhalid Al Mansoori
- SAStudio Arc Interiors
- BMBay View Tower management
Subcontractors on this project
Work orders, progress, certified to date and 10% retention held| Work order | Value | Progress | Certified | Retention | Status |
|---|---|---|---|---|---|
| Al Madar GypsumWO-TS-26-021 · gypsum & ceiling | 46,000 | 90% |
26,400 | 2,640 | Claim #3 to certify |
| Coolbreeze MEPWO-TS-26-022 · MEP | 42,000 | 63% |
26,400 | 2,640 | Insurance expired |
| ProCoat PaintingWO-TS-26-026 · painting | 18,200 | 20% |
4,200 | 420 | In progress |
| Elite JoineryWO-TS-26-027 · pantry joinery | 19,800 | 0% |
0 | 0 | Started today |
| 4 work orders | 126,000 | 57,000 | 5,700 |
Coolbreeze payments stay on hold until the renewed insurance certificate is uploaded. Second fix starts 11 Oct.
Equipment at site
Own tools, tracked by QR tag- Glass vacuum lifter (4-cup, 400 kg)Inspection 15 Oct
- Laser levelCalibration 20 Oct
- Makita cordless drill setOK
- Safety harnessInspection Nov
Rentals on hire
Charged to cost code 08 · equipment & rentalsSeptember2,600
1–6 Oct510
Total by 6 Oct3,110
September includes AED 50 delivery · 30 days × AED 85.
Extend the towers or move our own?
Glass installers need towers until about 14 Oct (8 more days, AED 680). Our own 6 m tower AST-TS-0031 frees up at TS-26-019 on 9 Oct — return one rented tower on 6 Oct and bring ours in.