LHPTechnical Services
6

Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct

TS-26-014 Gulf Horizon Properties PM Arun Kumar 10 Aug → 30 Oct 2026 LPO GHP/LPO/2026/0418
Next week needs 14 people a day — 9 are booked. Glass installation starts 7 Oct alongside joinery and painting. Shahid Iqbal (glass technician) is free from TS-26-016 after its snagging walk on 6 Oct; Ramesh Thapa has agreed.
Shahid Iqbal joins TS-26-014 on 7 Oct. With Elite Joinery and ProCoat, next week is planned at 14 people a day.
On site today
9
Own crew 7 of 7 · Elite Joinery 2
Subcontract work orders
AED126,000
4 work orders · 57,000 certified
Equipment at site
5
4 own · 1 rental due back 6 Oct
Own labour hours
1,247
To 30 Sep · AED 14,280 allocated

Own team

Today's GPS check-in · hours booked to this project in September
Employees
PersonRole on projectTodaySep hours
AK
Arun Kumar
Project Manager
Leads 6 projects · client & costs Site visit 2:00 PM Overhead
MR
Site Foreman · TS-E004
Runs the site · daily report · petty cash In 7:02 AM 176
VR
Vignesh Raman
Site Engineer
Drawings, RFIs, QA · shared with TS-26-019 In 7:05 AM 88
JJ
Jomon Joseph
Glass Technician
Glass partitions & doors · drill set AST-TS-0021 In 7:04 AM 92
RD
Ronald Dela Cruz
Glass Technician
Glass partitions · U-channels In 6:58 AM 108
KB
Krishna Bahadur
Carpenter
Skirting, doors, joinery support In 7:08 AM 120
RH
Rakib Hasan
Helper
Flooring & material handling In 7:01 AM 95
AK
Abdul Kareem
Helper · probation to 13 Mar 2027
Flooring & cleaning · joined 14 Sep In 7:03 AM 56
SI
Shahid Iqbal
Glass Technician · from TS-26-016
Glass installation, activity 7 From 7 Oct —
On site today: 7 of 7735

Weekly manpower

People per day on site · W1 = week of 10 Aug
1612840
W1
W2
W3
W4
W5
W6
W7
W8
W9

Own crew steady at 7; subcontract labour fell from 8 to 3 a day. Pale bar = plan for next week (8 own + 6 subcontract).

Labour hours & cost

From GPS timesheets · cost code 07
August512 h
September735 h
Avg per hour11.45
Allocated14,280
68%

AED 14,280 of the 21,000 own-labour budget used at 62% progress. Forecast 22,400 — see costs.

Client side

Who signs, who checks
  • KM
    Khalid Al Mansoori
    Facilities Director · Gulf Horizon
    Approver
  • SA
    Studio Arc Interiors
    Consultant · drawings, RFIs, certifies IPAs
  • BM
    Bay View Tower management
    Work permit to 31 Oct · loading bay

Subcontractors on this project

Work orders, progress, certified to date and 10% retention held
All
Work orderValueProgressCertifiedRetentionStatus
Al Madar GypsumWO-TS-26-021 · gypsum & ceiling 46,000
90%
26,400 2,640 Claim #3 to certify
Coolbreeze MEPWO-TS-26-022 · MEP 42,000
63%
26,400 2,640 Insurance expired
ProCoat PaintingWO-TS-26-026 · painting 18,200
20%
4,200 420 In progress
Elite JoineryWO-TS-26-027 · pantry joinery 19,800
0%
0 0 Started today
4 work orders126,00057,0005,700
Coolbreeze payments stay on hold until the renewed insurance certificate is uploaded. Second fix starts 11 Oct.

Equipment at site

Own tools, tracked by QR tag
Tools & equipment

Rentals on hire

Charged to cost code 08 · equipment & rentals
Rentals
September2,600
1–6 Oct510
Total by 6 Oct3,110

September includes AED 50 delivery · 30 days × AED 85.

Extend the towers or move our own?

Glass installers need towers until about 14 Oct (8 more days, AED 680). Our own 6 m tower AST-TS-0031 frees up at TS-26-019 on 9 Oct — return one rented tower on 6 Oct and bring ours in.

Shahid Iqbal assigned from 7 Oct
He moves from TS-26-016 to glass installation on TS-26-014 until 17 Oct. Mohammed Rafiq and Ramesh Thapa were told on WhatsApp.