LHPTechnical Services
6
Schedule · TS-26-014

Update progress

TS-26-014 · Office fit-out, Level 12 Bay View Tower

Bay View Tower, Business Bay · 10:36 AM Saves on the phone if signal drops
Viewing as Mohammed Rafiq · Site Foreman. This is the screen used on site: pick the activity, set the new %, add photos, save.

Activity

Only activities running this week are listed
Planned11 Sep → 4 Oct
Plan for today75%
Last update60% · 29 Sep
WhoOwn team
New progress *
Overall project progress moves from 62% to 63% (flooring is about 12% of the contract value).
Plan 4 Oct · +4 days · not on the critical path
Status
LPO-TS-26-119 Prime Flooring: 100 of 160 m² delivered, balance due 6 Oct.

Photos & drawing

Required for this activity
Photos required
4 photos attached2.8 MB · uploads on Wi-Fi or 4G
Vinyl laid in zone BZone B vinyl10:31 AM
Vinyl joint at the corridor thresholdCorridor threshold10:32 AM
Protection board over the new vinylFloor protection10:33 AM
FL-301 marked with the laid areaFL-301 marked up10:34 AM
Drawing for this activity
FL-301 Rev A · flooring layout Approved · code A

Who sees this update

The schedule recalculates as soon as you save

Khalid Al Mansoori sees the new % and these 4 photos on his schedule link. Notes and costs stay internal.

Partners see it in tonight's 9:00 PM WhatsApp summary.

Bay View Tower, Business Bay · within 40 m of site Fri 2 Oct 2026 · 10:36 AM
Mohammed Rafiq · GPS verified Cancel