Site reports

All sites today. Foremen submit from the phone by 10:00 AM; every report feeds the 9:00 PM WhatsApp summary to the partners.

Friday, 2 October 2026Sunny, 34°C5 active sitesUpdated 10:30 AM
TS-26-017 Oasis Walk has not sent today's report. Ramesh Thapa has 5 people tiling on site and the report was due at 10:00 AM. The crew is short of tile adhesive (PR-TS-26-0143 waiting for approval).
Reminder sent to Ramesh Thapa at 10:32 AM. He gets a WhatsApp message and an app notification. If the report is not in by 12:00 PM it goes to Arun Kumar automatically.
Reports in today
4/5
TS-26-017 pending
People on site
21
Own staff 14 · subcontract 7
22 of 24 staff present company-wide
Safety incidents
0
4 toolbox talks held · 16 attended
No near misses
Photos today
23
GPS and time stamped from the phone
Bay View Tower 6 · Barsha Pearl 8

All sites today

One daily report per site · manpower from the phone attendance check-in
SiteReported byOwn / subReportToday's workIssues
TS-26-014 · Bay View TowerLevel 12 · DPR-047 · 6 photos
MR
Mohammed Rafiq
Site Foreman
7 / 29 on site
9:40 AM Vinyl flooring zone B, 100 of 160 m²; pantry joinery delivered; corridor ceiling closing
TS-26-016 · Al Noor MedicalSnagging · handover 15 Oct · 5 photos
VR
Vignesh Raman
Site Engineer · lead Shahid Iqbal
2 / 13 on site
9:15 AM Snags 7 of 11 closed; door closers adjusted None
TS-26-017 · Oasis Walk G-249 days behind · last report 1 Oct, 6:10 PM
RT
Ramesh Thapa
Site Foreman
2 / 35 on site
PendingReminded 10:32 AM
Yesterday: floor tiling, 40% laid
TS-26-018 · Arabian Ranches 2Villa 23 · 4 photos
AH
Anwar Hossain
Installer
2 / 02 on site
8:55 AM Balustrade base channel, 12 of 18 m fixed None
TS-26-019 · Barsha PearlMobilizing · 8 photos
GP
Ganesh Pillai
Installer
1 / 12 on site
10:05 AM Window survey floors 3–5, 18 of 48 measured Generator pending
TS-26-020 Spice Route Kitchen starts 12 Oct and joins this list on its first site day. Attendance

Latest report · TS-26-014

DPR-TS-26-014-047 · Mohammed Rafiq · 9:40 AM · GPS Bay View Tower
Open
Weather
Sunny, 34°C (indoor works)
Manpower
Own crew 7 + Elite Joinery 2
Materials received
None today
Safety
Toolbox talk 7:30 AM · 9 attended
Incidents
None
Photos
6 · GPS and time stamped
Work done
  • Vinyl flooring, zone B
    100 of 160 m² laid · balance 60 m² delivered 6 Oct
  • Pantry joinery carcasses delivered
    Elite Joinery · activity 9 starts today
  • Corridor ceiling closing
    Al Madar Gypsum · activity 5 at 90%
  • Glass waits for PR-TS-26-0142
    Tempering 5 Oct, delivery 6 Oct
  • RFI-07 access panel location
    Open since 30 Sep · waiting for Studio Arc Interiors

Report compliance

This week · Sat 26 Sep – Fri 2 Oct · 6 site days
Mohammed Rafiq · TS-26-0146/6
Vignesh Raman · TS-26-0166/6
Anwar Hossain · TS-26-0185/6
Ganesh Pillai · TS-26-019 (from 28 Sep)5/5
Ramesh Thapa · TS-26-0174/6
Reports this week26 of 29
On time90%
Avg time in9:35 AM
Ramesh missed Wed 30 Sep and today. Anwar sent Sat 26 Sep late, next morning.

Not on site today

From the 7:00 AM attendance check-in
Attendance
  • IA
    Imtiaz Ali · Helper
    TS-26-017 crewSick, no certificate yet
    Absent
  • DB
    Dil Bahadur Rai · Glass Technician
    TS-26-014 crewBack 15 Oct
    Annual leave

Manpower by site

21 people · own staff and subcontract labour
Own staff 14Subcontract 7
TS-26-014 · Bay View Tower9
TS-26-017 · Oasis Walk5
TS-26-016 · Al Noor Medical3
TS-26-018 · Arabian Ranches 22
TS-26-019 · Barsha Pearl2
Hours from check-in and check-out are allocated to each project's own-labour cost every week.

Health & safety today

Toolbox talks recorded in each report
  • Handling glass panels
    TS-26-0147:30 AM
    9 attended
  • Working near a live clinic
    TS-26-0167:45 AM
    3 attended
  • Edge protection at the balcony
    TS-26-0187:40 AM
    2 attended
  • Ladder safety on window survey
    TS-26-0197:50 AM
    2 attended
  • Not reported yet
    TS-26-017comes with the daily report
    Pending
0 incidents · 0 near misses across all sites today

Latest photos from site

23 today · each photo is tagged with project, activity, GPS and time
TS-26-014 gallery
Vinyl flooring zone B at Bay View TowerFlooring zone BTS-26-014 Corridor ceiling at Bay View TowerCorridor ceilingTS-26-014
Adjusted glass door at Al Noor Medical CentreDoor closerTS-26-016
Balustrade base channel at Arabian Ranches villaBase channelTS-26-018
Existing windows surveyed at Barsha Pearl ResidenceWindow surveyTS-26-019
Glass partition snag check at Al Noor Medical CentreSnag checkTS-26-016

Why the 10:00 AM cut-off matters

Reports that arrive by 10:00 AM give procurement a full day to act on shortages. TS-26-017 has missed two reports this week and is also the site that ran out of adhesive and silicone. A short daily report would have flagged it a day earlier.

Reminder sent
Ramesh Thapa got a WhatsApp reminder to submit today's TS-26-017 report. Arun Kumar is copied.