Site reports
All sites today. Foremen submit from the phone by 10:00 AM; every report feeds the 9:00 PM WhatsApp summary to the partners.
TS-26-017 Oasis Walk has not sent today's report.
Ramesh Thapa has 5 people tiling on site and the report was due at 10:00 AM. The crew is short of tile adhesive (PR-TS-26-0143 waiting for approval).
Reminder sent to Ramesh Thapa at 10:32 AM.
He gets a WhatsApp message and an app notification. If the report is not in by 12:00 PM it goes to Arun Kumar automatically.
Reports in today
4/5
TS-26-017 pending
People on site
21
Own staff 14 · subcontract 7
22 of 24 staff present company-wide
Safety incidents
0
4 toolbox talks held · 16 attended
No near misses
Photos today
23
GPS and time stamped from the phone
Bay View Tower 6 · Barsha Pearl 8
All sites today
One daily report per site · manpower from the phone attendance check-in| Site | Reported by | Own / sub | Report | Today's work | Issues | |
|---|---|---|---|---|---|---|
| TS-26-014 · Bay View TowerLevel 12 · DPR-047 · 6 photos | MR Mohammed Rafiq Site Foreman |
7 / 29 on site |
9:40 AM | Vinyl flooring zone B, 100 of 160 m²; pantry joinery delivered; corridor ceiling closing | ||
| TS-26-016 · Al Noor MedicalSnagging · handover 15 Oct · 5 photos | VR Vignesh Raman Site Engineer · lead Shahid Iqbal |
2 / 13 on site |
9:15 AM | Snags 7 of 11 closed; door closers adjusted | None | |
| TS-26-017 · Oasis Walk G-249 days behind · last report 1 Oct, 6:10 PM | RT Ramesh Thapa Site Foreman |
2 / 35 on site |
PendingReminded 10:32 AM | Yesterday: floor tiling, 40% laid |
||
| TS-26-018 · Arabian Ranches 2Villa 23 · 4 photos | AH Anwar Hossain Installer |
2 / 02 on site |
8:55 AM | Balustrade base channel, 12 of 18 m fixed | None | |
| TS-26-019 · Barsha PearlMobilizing · 8 photos | GP Ganesh Pillai Installer |
1 / 12 on site |
10:05 AM | Window survey floors 3–5, 18 of 48 measured | Generator pending |
TS-26-020 Spice Route Kitchen starts 12 Oct and joins this list on its first site day.
Attendance
Latest report · TS-26-014
DPR-TS-26-014-047 · Mohammed Rafiq · 9:40 AM · GPS Bay View Tower- Weather
- Sunny, 34°C (indoor works)
- Manpower
- Own crew 7 + Elite Joinery 2
- Materials received
- None today
- Safety
- Toolbox talk 7:30 AM · 9 attended
- Incidents
- None
- Photos
- 6 · GPS and time stamped
Work done
- Vinyl flooring, zone B
- Pantry joinery carcasses delivered
- Corridor ceiling closing
Report compliance
This week · Sat 26 Sep – Fri 2 Oct · 6 site daysReports this week26 of 29
On time90%
Avg time in9:35 AM
Ramesh missed Wed 30 Sep and today. Anwar sent Sat 26 Sep late, next morning.
Not on site today
From the 7:00 AM attendance check-in- IAImtiaz Ali · HelperAbsent
- DBDil Bahadur Rai · Glass TechnicianAnnual leave
Manpower by site
21 people · own staff and subcontract labourOwn staff 14Subcontract 7
TS-26-014 · Bay View Tower9
TS-26-017 · Oasis Walk5
TS-26-016 · Al Noor Medical3
TS-26-018 · Arabian Ranches 22
TS-26-019 · Barsha Pearl2
Hours from check-in and check-out are allocated to each project's own-labour cost every week.
Health & safety today
Toolbox talks recorded in each report- Handling glass panels9 attended
- Working near a live clinic3 attended
- Edge protection at the balcony2 attended
- Ladder safety on window survey2 attended
- Not reported yetPending
0 incidents · 0 near misses across all sites today
Latest photos from site
23 today · each photo is tagged with project, activity, GPS and timeWhy the 10:00 AM cut-off matters
Reports that arrive by 10:00 AM give procurement a full day to act on shortages. TS-26-017 has missed two reports this week and is also the site that ran out of adhesive and silicone. A short daily report would have flagged it a day earlier.