Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct

TS-26-014 Gulf Horizon Properties PM Arun Kumar 10 Aug → 30 Oct 2026 LPO GHP/LPO/2026/0418
Two issues from today's report need someone in the office. Glass installation (activity 7) waits for PR-TS-26-0142 — approve today to keep the 6 Oct delivery. RFI-07 (access panel for FCU-3) still holds the corridor ceiling at grid D4.
Reports submitted
47 of 47 days
45 before 7 PM · 2 sent next morning
People on site today
9
Own crew 7 · Elite Joinery 2
Days without incident
47
47 toolbox talks · 0 near misses logged
Open issues from reports
2
Glass PR-0142 · RFI-07 access panel

DPR-TS-26-014-047 · today

Fri 2 Oct 2026 · submitted 9:40 AM by Mohammed Rafiq
SubmittedJust submitted
MR
Mohammed Rafiq
Site Foreman · mobile app
Bay View Tower, Business Bay · 9:40 AM
Weather Sunny 34°C
Manpower7 own + 2 sub
Materials inNone today
HSENo incidents
Work done
  • Vinyl flooring, zone B — 100 of 160 m² laid
    Activity 6 · FlooringBalance 60 m² due 6 Oct (LPO-TS-26-119)
    60%
  • Joinery carcasses delivered for the pantry
    Activity 9 · Joinery & pantryElite Joinery, 2 fitters
    Starts today
  • Ceiling closing in the corridor
    Activity 5 · Gypsum & ceilingGrid D4 left open for RFI-07
    90%
Issues & delays
  • Glass delivery depends on PR-TS-26-0142
    Tempering slot 5 Oct · delivery 6 Oct · View PR
  • RFI-07 access panel location
    Open since 30 Sep · Studio Arc · View RFI
Health & safety
Toolbox talk · 7:30 AM
Handling glass panels · 9 attended
Incidents / near misses
None
PPE check
All 9 compliant · harness for ceiling works
Read by Arun Kumar 9:52 AM · goes into the 9:00 PM WhatsApp summary to both partners

Earlier reports

One report per working day, Mon–Sat · newest first
All sites
046 Thu 1 Oct · 5:48 PM 9 people5 photos
Manpower
Own 7 · Al Madar 2
Materials received
Vinyl 100 m² from warehouse (GRN-TS-26-0098)
HSE
Toolbox talk: working on mobile towers · no incidents

Vinyl zone B started (64 m²). Gypsum boards closed in MR-3. Glass package measured on site against SD-GL-07 Rev B — PR-TS-26-0142 raised 4:12 PM for the glass partitions and doors.

045 Wed 30 Sep · 6:05 PM 11 people4 photos
Manpower
Own 7 · Al Madar 3 · ProCoat 1
Materials received
None
HSE
Toolbox talk: dust control · no incidents

Ceiling grid zone C completed. First paint coat in the corridor. FCU-3 access panel position clashes between A-201 and MEP-01 — RFI-07 raised by Vignesh Raman.

044 Tue 29 Sep · 6:20 PM 12 people3 photos
Manpower
Own 7 · Al Madar 3 · ProCoat 2
Materials received
Cutting discs & gloves (PC-TS-26-0228)
HSE
Toolbox talk: cutting tools · no incidents

Weekly client meeting #7 on site (Khalid Al Mansoori, Studio Arc). Carpet tiles zone A finished. Mist coat on the meeting-room walls.

043 Mon 28 Sep · sent next day Late4 photos
Manpower
Own 7 · Al Madar 3
Materials received
None
HSE
Toolbox talk: housekeeping · no incidents

Gypsum partitions for MR-3 framed. Shop drawing SD-GL-07 Rev C issued to Studio Arc for the extra glass in MR-3 (VO-02). Sent the next morning — no signal on Level 12 after 6 PM.

ReportDatePeopleMain workPhotosStatus
DPR-042Mohammed RafiqSat 26 Sep10Carpet tiles zone A, ceiling boards3On time
DPR-041Mohammed RafiqFri 25 Sep12Internal QA walk zone A, painting prep5On time
DPR-040Vignesh RamanThu 24 Sep13Gypsum MR-1/MR-2, ceiling grid zone B4On time
DPR-039Mohammed RafiqWed 23 Sep14Floor levelling zone A, MR-3 framing3On time
DPR-038Mohammed RafiqTue 22 Sep13Vacuum lifter arrived from TS-26-016, ceiling boards zone A4On time
Showing 10 of 47 reports

This week

28 Sep – 3 Oct · report due by 7 PM
  • Mon 28 Sep · DPR-043
    Sent 7:40 AM next day · no signal on Level 12
    Late
  • Tue 29 Sep · DPR-044
    6:20 PM · 12 people · 3 photos
    On time
  • Wed 30 Sep · DPR-045
    6:05 PM · 11 people · 4 photos
    On time
  • Thu 1 Oct · DPR-046
    5:48 PM · 9 people · 5 photos
    On time
  • Fri 2 Oct · DPR-047
    9:40 AM · 9 people · 6 photos
    On time
  • Sat 3 Oct
    Reminder to Rafiq at 6:30 PM
    Due

People on site

Daily average per week, from reports
7 Sep
15
14 Sep
13
21 Sep
12
28 Sep
10
5 Oct plan
14

Next week needs 14: glass installers, Elite Joinery and ProCoat together. Book the extra helper now — see Team.

Who gets the report

Sent automatically on submit
  • AK
    Arun Kumar
    Instant push · reviews issues
  • MP
    Managing Partner
    9:00 PM WhatsApp summary
  • IP
    Investor Partner
    9:00 PM WhatsApp summary
The client sees photos and % only, never the daily report.

Manpower is dropping while three trades start

Average headcount fell from 15 to 10 in three weeks. Glass, joinery and painting all run next week — without 14 people a day the 30 Oct handover slips further.

Daily report submitted — partners notified
DPR-TS-26-014-047 is saved with 6 photos and GPS stamp. Arun Kumar got it now; both partners get it in the 9:00 PM WhatsApp summary.