Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct
DPR-TS-26-014-047 · today
Fri 2 Oct 2026 · submitted 9:40 AM by Mohammed Rafiq- Vinyl flooring, zone B — 100 of 160 m² laid60%
- Joinery carcasses delivered for the pantryStarts today
- Ceiling closing in the corridor90%
- Glass delivery depends on PR-TS-26-0142
- RFI-07 access panel location
- Toolbox talk · 7:30 AM
- Handling glass panels · 9 attended
- Incidents / near misses
- None
- PPE check
- All 9 compliant · harness for ceiling works
Earlier reports
One report per working day, Mon–Sat · newest first046 Thu 1 Oct · 5:48 PM 5 photos
- Manpower
- Own 7 · Al Madar 2
- Materials received
- Vinyl 100 m² from warehouse (GRN-TS-26-0098)
- HSE
- Toolbox talk: working on mobile towers · no incidents
Vinyl zone B started (64 m²). Gypsum boards closed in MR-3. Glass package measured on site against SD-GL-07 Rev B — PR-TS-26-0142 raised 4:12 PM for the glass partitions and doors.
045 Wed 30 Sep · 6:05 PM 4 photos
- Manpower
- Own 7 · Al Madar 3 · ProCoat 1
- Materials received
- None
- HSE
- Toolbox talk: dust control · no incidents
Ceiling grid zone C completed. First paint coat in the corridor. FCU-3 access panel position clashes between A-201 and MEP-01 — RFI-07 raised by Vignesh Raman.
044 Tue 29 Sep · 6:20 PM 3 photos
- Manpower
- Own 7 · Al Madar 3 · ProCoat 2
- Materials received
- Cutting discs & gloves (PC-TS-26-0228)
- HSE
- Toolbox talk: cutting tools · no incidents
Weekly client meeting #7 on site (Khalid Al Mansoori, Studio Arc). Carpet tiles zone A finished. Mist coat on the meeting-room walls.
043 Mon 28 Sep · sent next day Late4 photos
- Manpower
- Own 7 · Al Madar 3
- Materials received
- None
- HSE
- Toolbox talk: housekeeping · no incidents
Gypsum partitions for MR-3 framed. Shop drawing SD-GL-07 Rev C issued to Studio Arc for the extra glass in MR-3 (VO-02). Sent the next morning — no signal on Level 12 after 6 PM.
| Report | Date | People | Main work | Photos | Status |
|---|---|---|---|---|---|
| DPR-042Mohammed Rafiq | Sat 26 Sep | 10 | Carpet tiles zone A, ceiling boards | 3 | On time |
| DPR-041Mohammed Rafiq | Fri 25 Sep | 12 | Internal QA walk zone A, painting prep | 5 | On time |
| DPR-040Vignesh Raman | Thu 24 Sep | 13 | Gypsum MR-1/MR-2, ceiling grid zone B | 4 | On time |
| DPR-039Mohammed Rafiq | Wed 23 Sep | 14 | Floor levelling zone A, MR-3 framing | 3 | On time |
| DPR-038Mohammed Rafiq | Tue 22 Sep | 13 | Vacuum lifter arrived from TS-26-016, ceiling boards zone A | 4 | On time |
This week
28 Sep – 3 Oct · report due by 7 PM- Mon 28 Sep · DPR-043Late
- Tue 29 Sep · DPR-044On time
- Wed 30 Sep · DPR-045On time
- Thu 1 Oct · DPR-046On time
- Fri 2 Oct · DPR-047On time
- Sat 3 OctDue
People on site
Daily average per week, from reportsNext week needs 14: glass installers, Elite Joinery and ProCoat together. Book the extra helper now — see Team.
Who gets the report
Sent automatically on submit- AKArun Kumar
- MPManaging Partner
- IPInvestor Partner
Manpower is dropping while three trades start
Average headcount fell from 15 to 10 in three weeks. Glass, joinery and painting all run next week — without 14 people a day the 30 Oct handover slips further.