LHPTechnical Services
6
Quotations

New quotation Draft

Price the work, check the margin and send it — Zenith Fitness, lead L-TS-26-089.

Budget quotation from the client's floor plan. Final measurements are taken at the site visit on Tue 6 Oct; if quantities change by more than 5% the system creates Rev 2 for you.

Client & job

Filled in from the lead — change if needed
Quotation number
Q-TS-26-064 next number · locked once sent · revisions become Rev 2, Rev 3 …
30 days — company default

Bill of quantities

What the client sees · rates from the price list, excl. VAT
Copy from a quotation
#DescriptionQtyUnitRate (AED)Amount
1 13,440
2 15,960
3 7,700
4 2,400
5 4,500
Subtotal · 5 lines44,000
VAT 5%2,200
Total incl. VATAED 46,200

Cost build-up

Internal — never printed on the quotation
Margin 22.5%
AED
Glass & mirrors from LHP Metals & Glass 16,910 · door hardware 3,200 · seals & silicone 2,190
AED
2 glass technicians + 1 helper, incl. supervision & transport
AED
None — all own team
AED
Site protection, insurance, delivery & office share
Estimated cost34,100
Selling price44,000
Margin (AED)9,900
Margin (%)22.5%

Terms & programme

Printed on the quotation · the template builds the schedule if the job is won
Advance AED 13,200 + VAT 660 = AED 13,860
Programme template
Templates are managed in Schedule templates.

Attachments & sending

The client gets a PDF and a link that shows when it was opened
Send to Omar Siddiqui by
Draft saved 10:52 AM Cancel