Created from the won quotation — code, budget and schedule are filled in for you. Check the details, attach the client's LPO and create.

Won: Q-TS-26-061 Rev 2 · Meridian Consultants · AED 465,000
Office fit-out, Level 7 Prism Tower · estimate margin 22.0% · programme 10 weeks · owner Rahul Menon.

Project

Copied from the quotation — adjust if needed
Project code
TS-26-021auto-generated · all costs, POs and invoices use this code
Used for GPS check-in, site photos and supplier deliveries.

Contract & client LPO

No project is opened without the client's purchase order
AED
VAT 5% 23,250 → AED 488,250 including VAT
Rev 1 was AED 489,000 · Rev 2 accepted

Dates & payment terms

From the quotation's commercial terms
Mobilization day
67 days · about 9½ weeks
%
AED 46,500 + VAT — recovered 10% from each progress invoice
%
Held by the client until the end of the defects period
Progress invoice (IPA) each month, paid 30 days after the client certifies it
months

Team

Availability is checked against current projects
Also managing 6 active projects
Available — covers the first two weeks on site
On TS-26-014 until 30 Oct — 12 days overlap with this start
Briefs the team on the BOQ and client promises

Budget from estimate

Locked by cost code when the project is created
Margin 22.0%
Cost codeBudget (AED)
Materials168,200
01 · Glass & aluminium72,600
02 · Flooring (carpet tiles + vinyl)46,300
03 · Gypsum, paint & general49,300
Subcontract119,400
04 · MEP modifications41,200
05 · Gypsum partitions & ceiling43,400
06 · Joinery (pantry, reception, storage)34,800
Labour, equipment & site75,000
07 · Own labour (from timesheets)46,800
08 · Equipment & rentals4,200
09 · Transport & logistics5,200
10 · Site overheads, preliminaries & insurance18,800
Total budget cost362,600
Materials 46%Subcontract 33%Own labour 13%Equipment & site 8%
Contract value465,000
Budget cost−362,600
Planned marginAED 102,400 · 22.0%

A purchase request that would take a cost code over its remaining budget is flagged for partner approval.

Schedule

Built from a template — every activity can be adjusted afterwards
Templates
Fitted to your dates. The template runs 81 days to handover; 19 Oct → 25 Dec gives 67, so activity durations are shortened by 17%. Handover is set to Fri 25 Dec.

Ms. Layla Haddad gets a read-only link — no costs, margins or internal notes.

Arun, Vignesh, Rafiq and the crew get the daily plan and photo reminders.

When you create the project

Everything below happens automatically
  • TS-26-021 opens in accounts, procurement and timesheets
  • Budget AED 362,600 locked across 10 cost codes
  • Advance invoice drafted: AED 46,500 + VAT 2,325 = 48,825
  • Schedule generated and shared with Layla Haddad
  • Client LPO and signed quotation filed in project documents