Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct

TS-26-014 Gulf Horizon Properties PM Arun Kumar 10 Aug → 30 Oct 2026 LPO GHP/LPO/2026/0418
PR-TS-26-0142 needs your approval — glass partitions & doors, AED 38,450. Investor Partner approved last night. Approve today so LHP Metals & Glass tempers on 5 Oct and delivers on 6 Oct.
Handover forecast 3 Nov (+4 days) if the glass is late. RFI-07 (access panel location) has been open since 30 Sep — the corridor ceiling can't close until Studio Arc Interiors answers. Open RFI-07

Schedule snapshot

Activities running now · actual vs plan for today
Full schedule
Planned today66%
Actual62%
Schedule index (SPI)0.94
Forecast handover3 Nov
5 · Gypsum partitions & ceiling · Al Madar · plan 100%90%
6 · Flooring (vinyl + carpet tiles) · plan 75%60%
7 · Glass partitions & doors · glass from LHP M&G · plan 55%30%
8 · Painting & finishes · ProCoat · plan 35%20%
9 · Joinery & pantry · Elite Joinery · starts today0%
Actual progressWhere it should be today
Done: mobilization, protection, demolition, MEP first fix · Next: MEP second fix from 11 Oct Update

Latest updates

Site reports, photos, approvals and client activity
Site reports
  1. Daily report DPR-TS-26-014-047
    Mohammed Rafiq · today 9:40 AM · 9 on site (7 own + 2 Elite Joinery) · sunny, 34°C
    Vinyl flooring zone B — 100 of 160 m² laid. Pantry joinery carcasses delivered. Ceiling closing in the corridor. Toolbox talk 7:30 AM “Handling glass panels” (9 attended), no incidents.
  2. 4 photos added to activity 6 · Flooring
    Mohammed Rafiq · today 9:32 AM · GPS-stamped at Bay View Tower
  3. Investor Partner approved PR-TS-26-0142 · 1 of 2
    yesterday 7:15 PM · mobile app · raised by Mohammed Rafiq at 4:12 PM
    “Approved — confirm M&G delivery date”
  4. Khalid Al Mansoori viewed the shared schedule
    Gulf Horizon Properties · yesterday 6:10 PM · asked to confirm the glass delivery date
  5. RFI-07 raised · access panel location
    Vignesh Raman · 30 Sep · waiting for Studio Arc Interiors
  6. VO-03 sent to client · acoustic laminated glass, Director's office
    Arun Kumar · 29 Sep · AED 12,750 · awaiting client
  7. Shop drawing SD-GL-07 Rev C submitted
    Vignesh Raman · 28 Sep · glass partitions · pending consultant approval

Key documents

Contract, insurance and programme
All documents

Money

Billing & collections · AED
Billing
Billed 57%Left to bill 173,700
Original contract386,000
VO-02 approved+18,600
Revised contract404,600
Billed to date (gross)230,900
Received (excl. VAT)137,030
Outstanding · INV-TS-26-0087104,679.75
Retention held by client11,545
Advance still to recover17,370

IPA-02 was certified on 30 Sep and is due on 30 Oct (amount incl. VAT).

IPA-03 · AED 86,126.25 · planned 25 Oct Prepare

Upcoming milestones

Next 4 weeks

Team

9 on site today · 7 own + 2 Elite Joinery
Team
  • AK
    Arun Kumar
    Project Manager
  • VR
    Vignesh Raman
    Site Engineer
  • MR
    Mohammed Rafiq
    Site Foreman
    7:02 AM
Crew on site
JJRDKBRHAK

Subcontractors