Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct
PR-TS-26-0142 needs your approval — glass partitions & doors, AED 38,450.
Investor Partner approved last night. Approve today so LHP Metals & Glass tempers on 5 Oct and delivers on 6 Oct.
Handover forecast 3 Nov (+4 days) if the glass is late.
RFI-07 (access panel location) has been open since 30 Sep — the corridor ceiling can't close until Studio Arc Interiors answers. Open RFI-07
Progress
62%
Plan for today 66%4 pts
Contract value
AED404,600
386,000 + VO-02 18,600
Billed 230,900 · received 137,030
Cost to date
AED168,450
56% of 301,000 budget · 61,200 committed
Forecast margin
22.6%
Above 22% target
Forecast final cost 313,200
Schedule snapshot
Activities running now · actual vs plan for todayPlanned today66%
Actual62%
Schedule index (SPI)0.94
Forecast handover3 Nov
Actual progressWhere it should be today
Done: mobilization, protection, demolition, MEP first fix · Next: MEP second fix from 11 Oct
Update
Latest updates
Site reports, photos, approvals and client activity-
Daily report DPR-TS-26-014-047Vinyl flooring zone B — 100 of 160 m² laid. Pantry joinery carcasses delivered. Ceiling closing in the corridor. Toolbox talk 7:30 AM “Handling glass panels” (9 attended), no incidents.
-
4 photos added to activity 6 · Flooring
-
Investor Partner approved PR-TS-26-0142 · 1 of 2“Approved — confirm M&G delivery date”
-
Khalid Al Mansoori viewed the shared schedule
-
RFI-07 raised · access panel location
-
VO-03 sent to client · acoustic laminated glass, Director's office
-
Shop drawing SD-GL-07 Rev C submitted
Key documents
Contract, insurance and programmeMoney
Billing & collections · AEDBilled 57%Left to bill 173,700
Original contract386,000
VO-02 approved+18,600
Revised contract404,600
Billed to date (gross)230,900
Received (excl. VAT)137,030
Outstanding · INV-TS-26-0087104,679.75
Retention held by client11,545
Advance still to recover17,370
IPA-02 was certified on 30 Sep and is due on 30 Oct (amount incl. VAT).
IPA-03 · AED 86,126.25 · planned 25 Oct
Prepare
Upcoming milestones
Next 4 weeks-
Needs youGlass on site from LHP M&G
- Insurance expiredMEP second fix starts
-
PlannedIPA-03 to 80%
- PlannedClient walkthrough
-
Fcst 3 NovHandover to Gulf Horizon
Team
9 on site today · 7 own + 2 Elite Joinery- AKArun Kumar
- VRVignesh Raman
- MR7:02 AMMohammed Rafiq
Crew on site
JJRDKBRHAK
Subcontractors
- 90%Al Madar Gypsum & Partitions
- Insurance expiredCoolbreeze MEP
- 20%ProCoat Painting
- Started todayElite Joinery Works