Every purchase request, cost, invoice, photo and site report is filed under the project code.

TS-26-021 is open — Office fit-out, Level 7 Prism Tower for Meridian Consultants. Budget AED 362,600 locked by cost code, an 11-activity schedule generated for 19 Oct → 25 Dec and the site team added to a WhatsApp group.
TS-26-014 needs its glass on site by 6 Oct. PR-TS-26-0142 (AED 38,450) is waiting for your approval — without it the handover moves from 30 Oct to 3 Nov.
TS-26-017 Oasis Walk is 9 days behind. The mall NOC came late and the client changed the design. Forecast handover 25 Oct, forecast margin 16.6% against the 22% target. Project profitability
Active projects
67
3 in progress · 2 starting · 1 snaggingTS-26-021 added · starts 19 Oct
Contract value (active)
AED1,363,9001,828,900
Includes approved VO-02 on TS-26-014
Still to bill
AED987,4001,452,400
≈ 4.3 months of billing at the current pace≈ 6.3 months of billing at the current pace
Avg forecast margin
21.421.6%
Target 22%weighted by contract value

All projects

Progress is weighted by BOQ value · budget used = cost to date ÷ budget
ProjectContract (AED)ProgressBudget usedMarginTeamStatus
TS-26-021 · Office fit-out, Level 7 Prism TowerMeridian Consultants · 19 Oct → 25 Dec 465,000
0%
11 activities scheduled
0%
0 of 362,600
22.0%
AKMR
Not started
TS-26-014 · Office fit-out, Level 12 Bay View TowerGulf Horizon Properties · 10 Aug → 30 Oct
404,600incl. VO-02
62%
plan 66%
56%
168,450 of 301,000
22.6%
AKMR
Glass needed by 6 Oct
TS-26-016 · Glass partitions & doors, Al Noor MedicalAl Noor Medical Centre · 27 Jul → 15 Oct 128,500
85%
plan 84%
85%
81,950 of 96,400
23.3%
AKSI
Snagging7 of 11 snags closed
TS-26-017 · Retail fit-out, Unit G-24 Oasis WalkUrban Threads Trading · 17 Aug → 25 Oct (was 16 Oct) 214,000
35%
plan 60%
49%
81,300 of 167,000
16.6%
AKRT
Delayed 9 days
TS-26-018 · Villa glass balustrade & showersMr. Daniel Brooks · 14 Sep → 30 Oct 76,800
20%
plan 20%
14%
8,150 of 58,400
22.9%
AKAH
On track
TS-26-019 · Aluminium windows replacement (48)Crescent Facilities Management · 28 Sep → 10 Dec 242,000
8%
plan 8%
5%
9,300 of 186,000
21.7%
AKGP
Mobilizing
TS-26-020 · Restaurant fit-out, Spice Route KitchenSpice Route Hospitality · 12 Oct → 15 Jan 2027 298,000
0%
advance PDC 15 Oct
0%
0 of 231,000
21.8%
AK
Starts 12 Oct
TS-26-008 · Office partitions, Atlas LogisticsAtlas Logistics FZE · completed 15 Jun 96,000
100%
DLP ended 30 Sep
98%
final cost 73,900
23.0%
AK
CompletedRelease retention 4,800
TS-26-011 · Café glass shopfront, Bean Theory CaféBean Theory Café · completed 21 Aug 54,000
100%
DLP to 21 Feb 2027
104%
final cost 43,100
20.2%
AK
CompletedBalance 5,600 overdue
Active total · 6 projects· 7 projects 1,363,9001,828,900 987,400 to bill1,452,400 to bill 21.4%21.6%
Completed projects stay listed until their retention is collected. Project profitability

Coming up

Deliveries, starts and handovers · next 30 days

Crews on site today

21 people · 14 own staff + 7 subcontract & others
Site reports
TS-26-014 · Bay View — 7 own + 2 Elite Joinery9
TS-26-017 · Oasis Walk — 2 own + 3 FloorTech5
TS-26-016 · Al Noor Medical — 2 own + 1 cleaner3
TS-26-018 · Arabian Ranches villa — 2 own2
TS-26-019 · Barsha Pearl — 1 own + 1 Crescent FM2
Reports in4 / 5
Photos today23
Incidents0
On leave / absent1 / 1

Crews free up in late October

TS-26-016 hands over on 15 Oct and TS-26-014 on 30 Oct. Line up the next award — Meridian Consultants decides on 10 Oct — so these crews keep billing in November.

Project TS-26-021 created
Schedule built from ‘Office Fit-out (Standard)’ and shared with the team.