Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct
SN-014-06 needs Coolbreeze MEP back on site by 8 Oct.
Their insurance certificate expired on 25 Sep, so payments are on hold and they may not be allowed on site after the building audit. Ask them for the renewed certificate before MEP second fix starts on 11 Oct.
Snags raised
67
Internal QA walks · zone A
Closed
4
3.5 days on average to close
Open
23
None overdue · next due 5–6 Oct
Handover
28 days
30 Oct · checklist 2 of 10 done
Internal QA snags
Raised by our own team before the client sees them-
Carpet tile edge lifting at the MR-1 doorNewDue 5 Oct
-
Ceiling tile misaligned near grid C4OpenDue 6 Oct
-
Downlight off-centre with the ceiling grid, MR-2OpenDue 8 Oct
-
Floor box cover not flush, MR-2Closed5 days
-
Gypsum joint crack above door D-04Closed4 days
-
Skirting gap at MR-1Closed3 days
-
Paint touch-up, corridor wallClosed2 days
A snag closes only with an "after" photo from the same spot · the client never sees this list
QA walks by zone
Internal first, then the client- Zone A · reception & meeting rooms
- BZone B · open office
- CZone C · pantry & director's office
- Client walkthrough
Who fixes what
Closed of raised, by companySubcontractor snags are checked before their next claim is certified.
Clear zone A before the glass arrives
Both open snags are at ceiling level. Fix them this week while the scaffold towers are still in zone A — from 7 Oct the towers move to the glass installation in zone B.
Handover checklist
Practical completion 30 Oct · 2 of 10 done20%
- Handover format and document list agreed
- Warranty letters requested
- Internal snag walks, zones A–C
- As-built drawings
- O&M manuals
- Test & commissioning certificates
- Final cleaning
- Keys, access cards & key register
- Client walkthrough
- Handover certificate signed
Retention release terms. Gulf Horizon holds 5% of each certified bill — AED 11,545 so far, about AED 20,230 on the revised contract of 404,600. It is released in full after the 12-month defects liability period (30 Oct 2027), once all client snags are closed and the DLP certificate is signed. See billing