SC-CL-TS-26-0019 Waiting for certification Approved · paying 15 Oct Returned to Al Madar

Al Madar Gypsum & Partitions · claim #3 on WO-TS-26-021, gypsum partitions & ceiling · TS-26-014 Bay View Tower

THTariq Hassan · 30 Sep, 5:20 PM Work up to 30 Sep Verified on site 1 Oct PM certifies + 1 partner
Verified on site at 90% — certify today and it is paid in the 15 Oct run. Al Madar's crew comes back on 5 Oct for the last 10% (corridor ceiling and bulkheads). ProCoat can only paint the corridor after that, so keeping them on site protects the 30 Oct handover.

Payment certificate issued — paid in the 15 Oct run

AED 13,545 to Al Madar by bank transfer from Emirates NBD ••4521. Arun Kumar and Tariq Hassan were notified; retention on this work order is now AED 4,140.

Returned to Al Madar today at 10:41 AM. Tariq Hassan got your note: fix the misaligned ceiling tiles at grid C4 and send photos. Vignesh Raman re-checks, then the claim comes back to you with the same number.
Payable on this claim
AED13,545
12,900 + VAT 645
Work done to date
90%
41,400 of 46,000 · measured on site
This claim, gross
AED15,000
Less retention 1,500 and back-charge 600
Payment
15 OctOn hold
If certified today · bank transfer
ScheduledENBD ••4521
Until Al Madar resubmits
  1. Submitted30 Sep
  2. Site check1 Oct · 90%
  3. 3PM certifiesArun Kumar
  4. 4Partner approvesYou
  5. 5Payment certificateAutomatic
  6. 6Paid15 Oct run
  1. Submitted30 Sep
  2. Site check1 Oct · 90%
  3. CertifiedToday 10:41 AM
  4. ApprovedToday 10:41 AM
  5. Payment certificateSent to Al Madar
  6. 6Paid15 Oct run
  1. Submitted30 Sep
  2. Site check1 Oct · 90%
  3. ReturnedToday 10:41 AM
  4. 4Partner approvesAfter resubmission
  5. 5Payment certificate
  6. 6Paid

Payment calculation

Claim #3 · work up to 30 Sep · AED
Retention 10% · VAT 5%
Work order value · WO-TS-26-02146,000.00
Work done to date · 90% verified41,400.00
Less certified in claims #1–#2−26,400.00
This claim, gross15,000.00
Less retention 10%−1,500.00
Less back-charge BC-TS-26-006−600.00
Net amount12,900.00
VAT 5% · TRN 100 3456 7812 9003645.00
Total payableAED 13,545.00
Work order value · AED 46,000
Certified before 26,400This claim 15,000Left 4,600
Certified after41,400
Left to claim4,600
Retention after4,140

On budget: cost code 05 (gypsum & ceiling) is budgeted at AED 46,000 — the same as the work order.

Measurement

Quantities measured on site against drawing A-201 Rev B
Matches site check
ItemCertified beforeThis claimTo dateDone
Gypsum partitions, double layer, acoustic410 m² × 55.00 = 22,550.00
15,400.00280 m²
4,895.0089 m²
20,295.00369 m²
90%
Suspended ceiling, gypsum + 600 × 600 tiles780 m² × 27.50 = 21,450.00
11,000.00400 m²
8,305.00302 m²
19,305.00702 m²
90%
Bulkheads, access panels & making good1 LS = 2,000.00
0.000%
1,800.0090%
1,800.0090%
90%
Total · WO 46,000.0026,400.0015,000.0041,400.0090%
Still open: 41 m² of partitions at MR-3 and 78 m² of corridor ceiling — Al Madar back on 5 Oct. Schedule

Site verification

Vignesh Raman · 1 Oct, 11:05 AM · GPS Bay View Tower
90% confirmed
VR
“Walked the floor with Sajid Mehmood from Al Madar. Laser-measured every wall and the open ceiling areas — their figures match ours. One snag open at grid C4, they fix it on 5 Oct.”
  • Partitions 369 of 410 m² measured
    Open: MR-3 walls (41 m²) — waiting for the glass line to be fixed
  • Ceiling 702 of 780 m² measured
    Open: corridor grid (78 m²) — closes after MEP checks
  • Matches the schedule — activity 5 at 90%
    Gypsum partitions & ceiling · 7 days behind plan
  • 1 snag open: ceiling tile misaligned near grid C4
    Not deducted — retention covers it · fix due 5 Oct

Back-charge BC-TS-26-006

Damaged glass panel, meeting room MR-2 · 26 Sep
−600
Fixed glass panel at MR-2 with a chipped bottom cornerChipped corner, MR-2 fixed panel26 Sep · 4:15 PM · Mohammed Rafiq

Al Madar's scaffold tower hit the fixed 12 mm panel at MR-2 while they closed the ceiling. The corner is chipped, so the panel has to be replaced.

Replacement panel, 1.2 m², from LHP Metals & Glass420.00
Remove and refit, own glass team · 4 h180.00
Back-chargeAED 600.00

Agreed by Sajid Mehmood WhatsApp, 1 Oct 11:20 AM

Documents

Attached to this claim
Payment certificate issued — payment scheduled 15 Oct
SC-CL-TS-26-0019 · AED 13,545 to Al Madar Gypsum. Arun Kumar and Tariq Hassan were notified; retention on WO-TS-26-021 is now AED 4,140.
Claim returned to Al Madar
Tariq Hassan got your note by e-mail and WhatsApp. Once the C4 tiles are fixed, Vignesh Raman re-checks and the claim comes back to you.