Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct
Export
Site overheads & consumables will finish 60% over budget (AED 6,400 vs 4,000).
AED 5,050 is already spent, mostly on the floor protection and night shift of the rejected VO-01. Keep petty-cash buys on this code under AED 300 a week.
PR-TS-26-0142 (AED 38,450 glass) still needs your approval.
It is already in the code 01 forecast, so approving it does not change the margin. Waiting does: 4 more days of supervision, scaffold hire and site costs ≈ AED 1,900.
Cost budget
AED301,000
10 cost codes · locked 10 Aug
Actual cost to date
AED168,450
56% of budget spent · progress is 62%
Committed, not billed
AED61,200
2 LPOs + balance of 3 work orders
Forecast final cost
AED313,200
+12,200 vs budgetVO-02 adds 13,400
Budget vs actual by cost code
AED excl. VAT · committed = LPOs and work orders not billed yet · variance = budget − forecast- 01 Materials – glass & aluminium3,500 under47% spent
- 02 Materials – flooring1,700 under63% spent
- 03 Materials – gypsum, paint & general600 under67% spent
- 04 Subcontract – MEPOn budget63% spent
- 05 Subcontract – gypsum & ceilingOn budget72% spent
- 06 Subcontract – joinery600 over0% spent
- 07 Own labour1,400 over68% spent
- 08 Equipment & rentalsOn budget74% spent
- 09 Transport & logistics200 over79% spent
- 10 Site overheads & consumables2,400 over126% spent
- VO-02 cost · glass partition MR-3Funded by VO-02
- Total12,200 over56% spent
Original scope forecasts AED 299,800 — AED 1,200 under budget. The 12,200 "over" is the VO-02 work the client is paying for.
Spent so far against each budget
Bar = actual as % of budget · black line = 100% of budgetForecast within budgetForecast over budgetAlready over budget
Forecast final cost · AED 313,200
what is still to comeSpent 168,450Committed 61,200PR-0142 awaiting approval 38,450Not yet ordered 45,100
Latest cost transactions
Everything coded to TS-26-014 · newest first-
PC-TS-26-0230 · Drill bits & anchors96.50Posted
-
Own labour · September timesheets8,416Posted
-
RNT-TS-26-013 · Scaffold towers, September hire2,600Posted
-
SC-CL-TS-26-0019 · Al Madar, September work6,800Accrued
-
PC-TS-26-0228 · Cutting discs & gloves142.00Posted
-
LPO-TS-26-119 · Vinyl flooring 160 m²9,800Committed
-
SH-2214 · Patch fittings & door closers4,000Posted
-
WO-TS-26-027 · Pantry & storage joinery19,800Committed
Bills post at 3-way match · petty cash on approval · labour at month end
Supplier bills