LHPTechnical Services
6

Purchase orders (LPO)

Every LPO starts from an approved purchase request. Follow each one through delivery, goods received and the supplier's bill.

LPO-TS-26-121 is a draft until PR-TS-26-0142 is approved. It goes to LHP Metals & Glass automatically the moment the second partner approves — no re-typing.
Open LPOs
5 · AED 99,430
3 of them with LHP Metals & Glass
Awaiting delivery
3 LPOs
Next: glass to Bay View Tower, 6 Oct
Partially delivered
1 LPO
Vinyl 100 of 160 m² · balance 6 Oct
Received, not billed
2 · AED 8,105
Accrued so project costs stay right

LPOs

Last 4 weeks · 8 orders · AED 140,870 excl. VAT
LPOSupplierAmountDeliveryBilling
LPO-TS-26-121 DraftTS-26-014 · Frameless glass partitions & doors
LHP Metals & GlassInter-companyNot sent yet
38,450
Waiting for approvalDue 6 Oct · tempering 5 Oct
Not started
LPO-TS-26-120TS-26-016 · Silicone & glazing accessories
Royal Silicone & SealantsIssued 30 Sep
1,980
100%
GRN-TS-26-0099 · 1 Oct · Shahid Iqbal
Awaiting billDelivered 1 Oct
LPO-TS-26-119TS-26-014 · Vinyl flooring 160 m²
Prime Flooring SolutionsIssued 28 Sep · RFQ
9,800
63%
100 of 160 m² · GRN-TS-26-0098 · balance 6 Oct
Awaiting billPart delivery · 6,125 received
LPO-TS-26-118TS-26-017 · Shopfront glass & aluminium entrance door
LHP Metals & GlassInter-companyIssued 24 Sep
26,800
In productionSO-MG-26-021 · delivery 9 Oct
Bills on delivery
LPO-TS-26-117TS-26-018 · Frameless balustrade 15 mm laminated + shower glass
LHP Metals & GlassInter-companyIssued 22 Sep
22,400
PlannedSO-MG-26-023 · cutting 5 Oct
Not due
LPO-TS-26-116TS-26-014 · 12 mm tempered glass, meeting rooms MR-1 & MR-2
Al Safa Glass TradingIssued 16 Sep
23,600
100%
GRN-TS-26-0095 · 19 Sep · chipped panel replaced 24 Sep
Payment awaiting approvalAS-INV-55821 · 24,780 incl. VAT
LPO-TS-26-115TS-26-014 · Aluminium profiles & accessories
Desert Aluminium ProfilesIssued 14 Sep
10,800
100%
GRN-TS-26-0097 · 18 Sep
Billed · PDC 18 OctDAP-7781 · 11,340 incl. VAT
LPO-TS-26-114TS-26-017 · Gypsum board, paint & general materials
BuildMart Building MaterialsIssued 11 Sep
7,040
100%
Delivered to site · 15 Sep
Billed · due 25 OctBM-90412 · 7,392 incl. VAT
Bills are matched to the LPO and goods received before payment (3-way match). Goods received

Deliveries this week

Foremen confirm with a delivery-note photo
  • Vinyl balance · 60 m²
    LPO-TS-26-119 · Prime Flooring · Al Quoz store
    Tue 6 Oct
  • Glass partitions
    LPO-TS-26-121 · M&G · Bay View Tower L12
    6 Oct if approved
  • Shopfront glass
    LPO-TS-26-118 · DN-MG-26-0043 · Oasis Walk G-24
    Fri 9 Oct
Goods are checked against the LPO on arrival. Receive goods

Inter-company with M&G

Our LPO becomes their sales order automatically
Open LPOs3
Value87,650
We owe now42,000
LPO-121 · 38,450LPO-118 · 26,800LPO-117 · 22,400

INV-MG-26-0031 (AED 42,000, due 14 Oct) is scheduled for payment on 12 Oct and matched in both companies' books.

Priced at M&G list −8%. Inter-company

Received, not yet billed

Booked as accrued cost on the project
LPO-TS-26-120 · Royal Silicone1,980
LPO-TS-26-119 · 100 of 160 m²6,125
AccruedAED 8,105

Why this matters

Costs show on TS-26-014 and TS-26-016 the day goods arrive — not weeks later when the bill comes in.

Bills are expected within 7 days. Supplier bills