Office fit-out, Level 12 Bay View Tower · Gulf Horizon Properties · programme Rev 3 of 2 Oct 2026

Rev 3 sent at 10:45 AM. Khalid Al Mansoori got it on WhatsApp and email, Studio Arc Interiors by email. You'll be notified when they open or acknowledge it.

Send to client

They get a read-only link — always the latest version

Recipients

Send by

Sent from Arun Kumar · replies come back to the project

Revision history

Every version sent to the client is kept with its acknowledgement
RevisionWhat changedSent toStatus
Rev 3 · 2 Octcurrent Flooring and glass partitions re-forecast; joinery starts 2 Oct Khalid Al Mansoori, Studio Arc Interiors Not sentSent 10:45 AM
Rev 2 · 18 Sep VO-02 glass partition & door for Meeting Room 3 added Khalid Al Mansoori, Studio Arc Interiors Acknowledged 19 Sep
Rev 1 · 25 Aug Ceiling and MEP sequence confirmed after strip-out Khalid Al Mansoori Acknowledged 26 Aug
Rev 0 · 11 Augbaseline Baseline from “Office Fit-out (Standard)” · 12 weeks, handover 30 Oct Khalid Al Mansoori, Studio Arc Interiors Acknowledged 12 Aug

Live link

Read-only · no login needed
Access
Anyone with the link · view only
Expires
30 Nov 2026 · one month after handover
Opened
14 times · last by Khalid Al Mansoori, 1 Oct 6:10 PM

What the client sees

Applies to the link, WhatsApp and PDF

Forecast dates stay internal until you confirm them with the client.

Always hidden
  • Costs, budgets and margins
  • Supplier and subcontractor prices
  • Internal notes, RFIs and approvals
  • Crew names and attendance

Client preview

Exactly what Khalid sees on his phone or laptop
Read-only
LHP
LHP Technical Services
Project schedule · Rev 3 · 2 Oct 2026
Prepared for Gulf Horizon Properties LLC

Office fit-out, Level 12 Bay View Tower, Business Bay

Overall progress62%
Activities complete4 of 11
Target handover30 Oct
Last site updateToday 9:40
Today
Activity
10 Aug17 Aug24 Aug31 Aug7 Sep14 Sep21 Sep28 Sep5 Oct12 Oct19 Oct26 Oct
1Mobilization & setup100%
2Site protection100%
3Demolition100%
4MEP first fix100%
Complete
5Gypsum & ceiling90%
6Flooring60%
7Glass partitions30%
30% · glass arrives 6 Oct
8Painting & finishes20%
9Joinery & pantry0%
Starts this week
10MEP 2nd fix & T&C0%
11Cleaning & snagging0%
◆Handover 30 Oct
  • Activities 1–4 complete
    Mobilization, protection, demolition, MEP first fix
  • Gypsum & ceiling
    28 Aug – 24 Sep
    90%
  • Flooring
    11 Sep – 4 Oct
    60%
  • Glass partitions & doors
    17 Sep – 12 Oct · glass arrives 6 Oct
    30%
  • Painting & finishes
    24 Sep – 15 Oct
    20%
  • Joinery, MEP second fix, cleaning
    1 Oct – 29 Oct · starting now
  • Handover
    Friday 30 October 2026
Latest photos
Vinyl flooring in zone BZone B flooringtoday 9:32 AM
Corridor ceilingCorridor ceilingtoday 9:20 AM
Glass partition, meeting room 1Meeting room 11 Oct
First coat of paintPainting first coat30 Sep
Comments
KA
Please confirm the glass delivery date — our tenant walkthrough is on 28 Oct.
Khalid Al Mansoori1 Oct, 6:14 PM
AK
Glass is being tempered on 5 Oct, installation from 7 Oct. Handover stays 30 Oct.
Arun Kumar1 Oct, 7:05 PM
KA
Noted, thanks. Please share photos once the glass is in.
Khalid Al Mansoori1 Oct, 7:22 PM
Rev 2 acknowledged by Khalid Al Mansoori · 19 Sep Rev 3 not sent yet Rev 3 sent today 10:45 AM · waiting for acknowledgement
Add a comment Acknowledge Rev 3
Costs, margins, supplier prices and internal notes are never shown on this page.
Schedule shared with Khalid Al Mansoori on WhatsApp and email
Studio Arc Interiors received it by email. You'll be notified when they open it.
Link copied
erp.lhp-technical.ae/s/TS26014-7Kq2 — view only, expires 30 Nov 2026.