Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct
Glass partitions are 25 points behind plan and on the critical path.
Approve PR-TS-26-0142 today and LHP Metals & Glass tempers on 5 Oct — the handover holds at 30 Oct. Without it the handover moves to 3 Nov.
Actual progress
6263%
Plan for today 66%4 pts3 pts
Schedule index (SPI)
0.940.95
Earned ÷ planned progress · below 1.00 means behind
Forecast handover
3 Nov
+4 daysplanned Fri 30 Oct
Activities done
4 / 11
5 running · 2 not started
Programme · Rev 3
Bars run from actual start to forecast finish · grey line = baseline shared with the client on 11 Aug
Today
Activity
AugSepOct
1Mobilization
2Protection
3Demolition
4MEP 1st fix
5Gypsum
6Flooring
7Glass
7aGlass supply
8Painting
9Joinery
10MEP 2nd fix
11Cleaning
◆Handover
Done
Late
Behind plan
Own team
Subcontractor
LHP Metals & Glass
Baseline
Milestone
Today, 2 Oct
Client view last opened by Khalid Al Mansoori · 1 Oct, 6:10 PM
Share with client
Schedule health
Why the handover is at risk — and what fixes itPlanned for today66%
Actual (weighted by BOQ value)62%63%
Critical path
Activity 7Glass partitions30% · glass on site 6 Oct
Activity 8Painting final coatstarts after glass is fixed
Activity 11Cleaning & snagging9 days
MilestoneHandover 30 Octforecast 3 Nov
What fixes it: approve PR-TS-26-0142 today
LHP Metals & Glass tempers on 5 Oct, glass is on site on 6 Oct, the crew installs 7–12 Oct and painting finishes behind it — the handover stays on 30 Oct and SPI returns to about 0.98 within a week.
Other risks
- RFI-07 open since 30 Sep — corridor ceiling can't close
- Coolbreeze MEP insurance expired on 25 Sep
- Bay View Tower work permit valid to 31 Oct
Next 14 days
Look-ahead for the site team · 2–16 Oct- TodayJoinery starts — pantry carcasses
-
Needs youGlass tempering at LHP Metals & Glass
- WaitingClose corridor ceiling
- DeliveryGlass + 60 m² vinyl delivered
-
ReturnScaffold towers off-hire
- Own teamGlass installation restarts
- InsuranceMEP second fix starts
- PlanGlass partitions complete
Activities
Template “Office Fit-out (Standard)” v3 · photos are required when updating site activities| Activity | Planned | Actual / forecast | Progress | Status | Photos | Drawings | |
|---|---|---|---|---|---|---|---|
| 1–4 · Done by 4 SepMobilization, site protection, demolition and MEP first fix · 45 photos · drawings A-101, MEP-01 | |||||||
| 5 · Gypsum partitions & ceilingAl Madar Gypsum · subcontractor | 28 Aug – 24 Sep | Forecast 5 Octcorridor ceiling waits for RFI-07 |
90% |
Late · 7 working days | 14 | A-201 | Update |
| 6 · Flooring (vinyl + carpet tiles)Own team · Prime Flooring supply | 11 Sep – 4 Oct | Forecast 8 Oct60 m² vinyl arrives 6 Oct |
60% 70% |
Behind planUpdated 10:36 AM · 4 photos |
913 | FL-301 | Update |
| 7 · Glass partitions & doorsOwn team · glass from LHP Metals & Glass | 17 Sep – 12 Oct | Forecast 16 Oct12 Oct if PR-0142 is approved today |
30% |
At risk · glass | 6 | Update | |
| 8 · Painting & finishesProCoat Painting · subcontractor | 24 Sep – 15 Oct | Forecast 19 Octfinal coat after glass |
20% |
Behind plan | 4 | — | Update |
| 9 · Joinery & pantryElite Joinery · subcontractor | 1 – 18 Oct | Started 2 Octforecast 18 Oct |
0% |
Starts today | 0 | JN-401 | Update |
| 10 · MEP second fix, testing & commissioningCoolbreeze MEP · subcontractor | 11 – 22 Oct | On plan | 0% |
Not startedInsurance expired 25 Sep |
0 | MEP-01 | |
| 11 · Cleaning, snagging & handoverOwn team | 21 – 29 Oct | Forecast 25 Oct – 2 Nov | 0% |
Not started | 0 | — | |
| ◆ Handover to client · Fri 30 Oct | Tue 3 Nov · +4 days | ||||||
| Overall · weighted by BOQ value | 66% planned | 62% actual63% actual | 7882 |