LHPTechnical Services
6

Office fit-out, Level 12 Bay View Tower Glass needed by 6 Oct

TS-26-014Gulf Horizon PropertiesPM Arun Kumar10 Aug → 30 Oct 2026LPO GHP/LPO/2026/0418
RFI-07 is open since 30 Sep — where does the access panel for FCU-3 go? A-201 and MEP-01 disagree. Until Studio Arc answers (due 3 Oct), the corridor ceiling stays open at grid D4.
The Bay View Tower work permit ends on 31 Oct. If the handover moves to 3 Nov, ask the building management for an extension by 24 Oct. Check the schedule
Drawings
7
6 approved · SD-GL-07 Rev C with consultant
Submittals
9
8 approved · MS-09 pending (VO-03)
Open RFIs
12 of 78
Consultant answers in 2.3 days on average
Work permit
29 days left
Valid to 31 OctBay View Tower
DrawingRevApprovalDateFile
A-101 · Floor plan, Level 12Studio Arc Interiors · for constructionRev C · 12 AugCA · Approved12 AugPDF
A-201 · Reflected ceiling planComments: access panels per MEP-01Rev B · 20 AugBB · With comments20 AugPDF
FL-301 · Flooring layoutCarpet tiles + vinyl zones A–CRev A · 25 AugAA · Approved25 AugPDF
SD-GL-07 · Glass partition shop drawingRev C adds MR-3 (VO-02) · Rev B, code B, still in useRev C · 28 SepCWith consultant28 SepPDF
SD-GL-08 · Glass door & hardwarePatch fittings and floor springs per MS-07Rev A · 15 SepAA · Approved15 SepPDF
JN-401 · Pantry joineryElite Joinery · fabrication startedRev A · 22 SepAA · Approved22 SepPDF
MEP-01 · Lighting & power layoutCoolbreeze MEPRev B · 18 AugBA · Approved18 AugPDF

Approval codes: A approved · B approved with comments · C revise and resubmit · D rejected. The site team only sees the current revision; older revisions are kept with a "superseded" stamp.

Contract sum
AED 386,000 + VO-02 18,600
Client LPO
GHP/LPO/2026/0418 · 4 Aug
Programme
10 Aug → 30 Oct 2026
Advance
10% · recovered 10% per IPA
Retention
5% · released after 12-month DLP
Payment terms
30 days from certification
Contract documents are visible to partners, the project manager and accounts only. The client portal shows the LPO and certificates, never our costs.
SubmittalSupplierSubmittedStatus
MS-09 · Acoustic laminated glass 6+6 mmFor VO-03, Director's office · data sheet + sound testLHP Metals & Glass · submitted 29 SepLHP Metals & Glass29 SepPending
MS-08 · Pantry laminate & worktopSample boardElite Joinery · submitted 15 SepElite Joinery15 SepApproved 22 Sep
MS-07 · Patch fittings SS 304 satinGlass doors · sample + catalogueStar Hardware · submitted 4 SepStar Hardware4 SepApproved 10 Sep
MS-06 · Emulsion paint, 2 coloursColour drawdownsProCoat Painting · submitted 27 AugProCoat Painting27 AugApproved 2 Sep
MS-05 · Vinyl flooring 2 mm, oakPantry and corridorsPrime Flooring · submitted 21 AugPrime Flooring21 AugApproved 28 Aug
MS-04 · Carpet tiles 50 × 50, charcoalOpen office and meeting roomsPrime Flooring · submitted 21 AugPrime Flooring21 AugApproved 28 Aug
MS-03 · LED panels & downlightsLighting scheduleCoolbreeze MEP · submitted 12 AugCoolbreeze MEP12 AugApproved 18 Aug
MS-02 · Ceiling tiles 600 × 600Mineral fibre, tegular edgeAl Madar Gypsum · submitted 11 AugAl Madar Gypsum11 AugApproved 14 Aug
MS-01 · Gypsum board 12.5 mm & studsPartitions, double layerAl Madar Gypsum · submitted 11 AugAl Madar Gypsum11 AugApproved 14 Aug

RFI-07 · Access panel location, corridor ceiling

Raised 30 Sep by Vignesh Raman · to Studio Arc Interiors · answer due 3 Oct
Open · 2 days

Question. A-201 Rev B shows the corridor access panel at grid C4, but the FCU-3 valves on MEP-01 Rev B sit at grid D4. Please confirm the panel position and size (600 × 600 or 450 × 450) so the ceiling can be closed.

Impact. About 2 m² of corridor ceiling left open. No cost yet; 1 day if the answer comes after 6 Oct.

RFIRaisedAnsweredStatus
RFI-08 · Pantry sink position vs JN-401Raised today by Vignesh Raman2 OctDue 5 OctOpen
RFI-07 · Access panel location, corridorGrid C4 vs D430 SepDue 3 OctOpen
RFI-06 · Door hardware finish“Satin SS 304 to match the patch fittings (MS-07)”18 Sep20 SepClosed
RFI-05 · Skirting height in meeting rooms100 mm aluminium9 Sep11 SepClosed
RFI-04 · Manifestation film designFrosted band 100 mm at 1,000 and 1,500 mm2 Sep4 SepClosed
RFI-01 to RFI-03 · Setting-out & existing servicesAnswered during strip-outAugAugClosed
  • Work permit · Bay View Tower management
    BVT-FO-26-02129 access cards issuedextend by 24 Oct if handover slips
    Valid to 31 Oct
  • After-hours works permit · October
    BVT-AH-2610-118uploaded just nownoisy works 7 PM – 11 PM
    Valid to 31 Oct
  • After-hours works permit · September
    BVT-AH-2609-097used for demolition and core drilling
    Ended 30 Sep
  • Civil Defence approval · fire alarm changes
    Submitted by Coolbreeze MEPapproved 26 Sep
    Approved
  • Loading bay slot · glass delivery
    6 Oct, 7:00 – 8:00 AMgoods lift booked for 2 hours
    Booked

The October after-hours permit was approved by the building on 1 Oct — upload the copy so night works can continue.

MOM #7 · weekly site meeting · 29 Sep

11:00 AM at site · Khalid Al Mansoori (Gulf Horizon), Studio Arc Interiors, Arun Kumar, Vignesh Raman, Mohammed Rafiq

PointAction byDueStatus
Glass partitions: SD-GL-07 Rev C (with MR-3) submitted; glass from LHP Metals & Glass on 6 Oct once the PR is approvedArun Kumar2 OctOpen
VO-03 acoustic glass for the Director's office — price to be sent todayRahul Menon29 SepDone
Access panel clash at FCU-3 — raise an RFIVignesh Raman30 SepDone
Client walkthrough 28 Oct, handover 30 Oct confirmedGulf Horizon28 OctPlanned
MOM-07 signed.pdfNext meeting #8 · Mon 6 Oct, 11:00 AM
MOM #6 · weekly site meeting · 22 Sep

VO-02 (MR-3 partition) approved 18 Sep — shop drawing to be revised. Ceiling closing in zone A. Carpet tiles start 24 Sep. MOM-06.pdf

MOM #5 · weekly site meeting · 15 Sep

Extra meeting-room partition asked for by e-mail on 9 Sep priced as VO-02 — sent for approval. Joinery drawing JN-401 to be issued by 22 Sep. MOM-05.pdf

Add a document

Drawings, permits, minutes, photos of paperwork
Upload with details

Waiting on others

Chased automatically every 2 days

Recently added

Last 7 days
  1. After-hours permit · October
    Just now · you · Permits
  2. RFI-08 · pantry sink position
    Just now · sent to Studio Arc
  3. Payment certificate IPC-02
    30 Sep · Joseph Mathew · Contract
  4. RFI-07 raised
    30 Sep · Vignesh Raman · RFIs
  5. MOM #7 and MS-09
    29 Sep · Arun Kumar
  6. SD-GL-07 Rev C
    28 Sep · Vignesh Raman · Drawings
The client portal shows approved drawings, minutes and permits only.
Uploaded to Permits
After-hours works permit, October (BVT-AH-2610-118) is filed under TS-26-014. Mohammed Rafiq and Vignesh Raman were notified; you get a reminder on 24 Oct.
RFI-08 sent to Studio Arc Interiors
Answer due 5 Oct. It is linked to JN-401 and shows in the RFIs tab and in tomorrow's site report.