Subcontractors
Work orders, claims, retention and documents in one place. No subcontractor is paid without a certified claim and valid insurance.
Coolbreeze MEP — insurance certificate expired on 25 Sep.
Payment of AED 8,400 and any new work are blocked until a valid certificate is uploaded. Their MEP second fix on TS-26-014 is due to start on 11 Oct.
Al Madar claim #3 — AED 13,545 — waiting for certification.
Vignesh Raman verified 90% on site yesterday. Certify it so the crew comes back on 5 Oct to close the corridor ceiling before painting.
Review SC-CL-TS-26-0019
Active subcontractors
5
On 2 projects · 7 on the approved list
Open work orders
AED164,100185,500
6 work orders · excl. VAT
+1 pending approval7 work orders
Certified, not yet paid
AED31,200
8,400 on holdrest due 21 Oct
Retention held
AED10,520
Paid back after handover and defects periods
Approved subcontractors
Amounts in AED, excl. VAT · certified amounts are net of retention| Subcontractor | Open work orders | Value | Certified, unpaid | Retention | Documents | Rating | |
|---|---|---|---|---|---|---|---|
| Al Madar Gypsum & Partitions LLCGypsum partitions & ceilings · Tariq Hassan | 2 work ordersTS-26-014 · TS-26-017 |
74,500 | 18,600+ claim #3 to certify |
ValidInsurance to 30 Nov |
|||
| Coolbreeze MEP Services LLCHVAC, electrical & plumbing · Anil Varma | WO-TS-26-022TS-26-014 · MEP |
42,000 | 8,400On hold |
Insurance expiredSince 25 Sep · payments blocked |
|||
| ProCoat Painting ContractingPainting & finishes · Ravi Shankar | WO-TS-26-026TS-26-014 · painting |
18,200 | 4,200Due 21 Oct |
ValidInsurance to 18 Mar 2027 |
|||
| Elite Joinery Works LLCJoinery, pantry & reception desks · Joseph D'Costa | WO-TS-26-027TS-26-014 · joinery |
19,800 | 0Started on site today |
ValidInsurance to 4 Jul 2027 |
|||
| FloorTech InstallersFlooring installation, labour only · Manoj Bhatt | WO-TS-26-025TS-26-017 · tiling |
9,600 | 0First claim 20 Oct |
ValidInsurance to 12 Feb 2027 |
|||
| LHP Metals & Glass Industries LLCGlass processing & aluminium fabricationInter-company · group | Supplies through LPOsBilled as a supplier |
— | — | Group companyLicence due 28 Oct |
|||
| Skyline Scaffolding ServicesScaffolding & mobile towers · Dennis Fernandes | 2 towers on hireRNT-TS-26-013 |
0 | 0 | ValidInsurance to 9 Jan 2027 |
|||
| 164,100 | 31,200 | 10,520 |
Open work orders
Progress is work done on site, checked by the site engineer| Work order | Project | Value (AED) | Work done | Status |
|---|---|---|---|---|
| ProCoat PaintingWO-TS-26-028 | TS-26-020Spice Route Kitchen |
21,400 | 0% |
Pending approval |
| ProCoat PaintingWO-TS-26-028 | TS-26-020Spice Route Kitchen |
21,400 | 0% |
Draft |
| Al Madar GypsumWO-TS-26-021 | TS-26-014Bay View Tower |
46,000 | 90% |
Claim #3 to certify |
| Coolbreeze MEPWO-TS-26-022 | TS-26-014Bay View Tower |
42,000 | 60% |
On hold · insurance |
| ProCoat PaintingWO-TS-26-026 | TS-26-014Bay View Tower |
18,200 | 20% |
In progress |
| Elite JoineryWO-TS-26-027 | TS-26-014Bay View Tower |
19,800 | 0% |
Started today |
| Al Madar GypsumWO-TS-26-024 | TS-26-017Oasis Walk G-24 |
28,500 | 40% |
Project delayed |
| FloorTech InstallersWO-TS-26-025 | TS-26-017Oasis Walk G-24 |
9,600 | 25% |
In progress |
| 164,100185,500 |
Payments due
Certified claims · net of retention, excl. VAT- AMAl Madar · claim #212,60021 Oct
- AMAl Madar · claim #16,00021 Oct
- CBCoolbreeze MEP · claim #28,400On hold
- PCProCoat Painting · claim #14,20021 Oct
-
Al Madar · claim #312,900To certify
Certified: AED 31,200 · already in the 30-day commitments
Retention held
10% of every claim · AED 10,520AED 2,900 of Al Madar's retention (TS-26-008, Atlas Logistics) can be released now the defects period ended on 30 Sep — once Atlas pays our own AED 4,800 retention.
Before a subcontractor works on site
Checked on every work order and payment · expired documents block both- Valid trade licence on file
- Contractor's all risk / third-party insurance, at least AED 1 million
- Workmen's compensation for their own workers
- Monthly WPS salary proof before each claim is paid
- Emirates ID, site pass and safety induction for every worker
- Signed work order with retention, back-charge and delay clauses
Expiring in the next 60 days
- CBExpired 25 SepCoolbreeze MEP — insurance certificate
- AM30 NovAl Madar — CAR / third-party insurance
Ratings
Scored by the site engineer after every claim · out of 5Time is the weak spot
Quality scores average 4.4, but on-time scores average 3.9. Al Madar fell 7 days behind on TS-26-014 after moving its crew to another site for a week. Add a delay clause (AED 150 a day) to new work orders.
WO-TS-26-028 sent for approval
ProCoat Painting · TS-26-020 Spice Route Kitchen · AED 21,400. Above AED 5,000, so both partners approve; ProCoat then signs it in the portal.Reminder sent to Coolbreeze MEP
An upload link went to their office by e-mail and WhatsApp. The AED 8,400 payment and site access stay blocked until a valid certificate is approved.