LHPTechnical Services
6
Subcontractors

New work order

Scope, prices, retention and payment terms in one document. Above AED 5,000 both partners approve before it goes to the subcontractor.

Subcontractor

Only subcontractors with valid documents can be chosen
WO-TS-26-028 auto-numbered · used on every claim, payment and retention entry
Coolbreeze MEP Services can't receive new work orders. Their insurance certificate expired on 25 Sep — upload a valid certificate first. Ask Coolbreeze for the certificate
ProCoat checks: Trade licence to 3 Jun 2027 Insurance to 18 Mar 2027 WPS proof Sep On-time score 3.4

Project & scope

Linked to the project schedule and budget
Spice Route Hospitality · 12 Oct 2026 → 15 Jan 2027 · contract AED 298,000
From the template "Retail / F&B Shop Fit-out"
8 working days, as in the schedule · ends before signage and the Civil Defence inspection

Bill of quantities

Measured rates · claims are paid on measured work only
5 lines
ItemQtyUnitRate (AED)Amount
9,000.00
5,460.00
3,910.00
1,680.00
1,350.00
Add line
Rates checked. Emulsion at 12.50/m² and enamel at 140 per door match ProCoat's current order on TS-26-014 (WO-TS-26-026). The epoxy rate is new — 2 other quotes are on file (27.50 and 29.00).
Work order value21,400.00
VAT 5% · added on each claim1,070.00
Total incl. VATAED 22,470.00

Commercial terms

Standard LHP subcontract terms · change only if agreed
%
Held from every claim · AED 2,140 on the full order
AEDper day
Capped at 10% of the work order value
Before work starts

Drawings & documents

Sent to ProCoat with the work order

Budget & approval

Checked automatically before it is sent
Within budget
Painting & finishes — AED 1,600 left ✓
This work order 93%Left 7%
Budget line (TS-26-020)23,000
This work order21,400
Left after1,600

From the won estimate for Spice Route Kitchen (cost AED 231,000, margin 22.5%).

AED 21,400 → both partners
  1. You submit
    Arun Kumar checks scope & budget
  2. Both partners approve
    Managing & Investor Partner · WhatsApp + app
  3. ProCoat signs in the portal
    E-signature · documents re-checked
  4. Work starts 1 Dec
    After the site safety induction
≤ 5,000 one partner> 5,000 both partners
Draft saved 10:38 AM Cancel