Glass vacuum lifter 400 kg In useOut of use

AST-TS-0012 · 4-pad battery vacuum lifter for glass panels up to 400 kg · lifting equipment

TS-26-014 · Bay View Tower L12 Mohammed Rafiq Bought 12 Jul 2024 Book value AED 4,950
Lifting certificate expires on 15 Oct — in 13 days. The lifter is needed at TS-26-014 until handover on 30 Oct (glass partitions from 7 Oct). Without a valid certificate it cannot be issued and the Bay View Tower HSE team will stop it on site.
Inspection booked — Fri 9 Oct, 8:00 AM at Bay View Tower, Level 12. Emirates Lifting Inspection Services will examine and load-test the lifter on site (about 1 hour, AED 350). Mohammed Rafiq was asked to have it charged with clean pads. The new certificate will be attached here automatically.
Out of use — problem reported by you at 10:44 AM. Do not lift glass with AST-TS-0012 until Sunil Perera has checked it. The glass crew at TS-26-014 can carry on with the 4 hand suction lifters on site.

Asset details

Lifting equipment · tagged on purchase, 12 Jul 2024
Edit
Glass vacuum lifter with four suction padsAST-TS-0012Photo at issue · 22 Sep 2026
Make & model
GlassMate VL-400 DC
Serial no.
VL4-24-05517
Safe working load
400 kg
Pads
4 × 250 mm rubber
Power
12 V battery · low-vacuum alarm
Own weight
38 kg
CostAED6,800
Depreciated to dateAED1,850
Book valueAED4,950
Internal hireAED60 a day
Bought from
Gulf Glazing Tools · inv. GGT-2407-118
Depreciation
Straight line · 8 years
Warranty
Ended 11 Jul 2026
Cover on site
Contractor's plant · CAR-26-0418

Where it has been

Every move is signed on the phone · newest first
Move
  1. Since 22 Sep 2026 · 11 days · custodian Mohammed Rafiq
    Moved straight from Al Noor Medical. Checked on arrival by Vignesh Raman — pads, alarm and vacuum hold OK.
  2. TS-26-016 · Al Noor Medical Centre, Jumeirah 1
    21 Aug – 21 Sep 2026 · 32 days · Shahid Iqbal
  3. TS-26-011 · Bean Theory Café shopfront, Al Wasl Rd
    4 – 20 Aug 2026 · 17 days · Ramesh Thapa
  4. Warehouse · Al Quoz — idle
    16 Jun – 3 Aug 2026 · 49 days · battery replaced 18 Jun
  5. TS-26-008 · Atlas Logistics offices, Jebel Ali
    12 May – 15 Jun 2026 · 35 days · Mohammed Rafiq
  6. 11 earlier jobs, Jul 2024 – Apr 2026
    Including TS-25-006 Gulf Horizon lobby glass works · before day-by-day tracking started
  7. Bought and tagged
    12 Jul 2024 · AED 6,800 · received by Mohammed Rafiq

Inspection & maintenance

Thorough examination every 12 months · weekly pre-use check by the foreman
WorkByResultCost (AED)
Annual thorough examination & load testDue by 15 Oct 2026 · not booked yet Third-party inspector Due in 13 days ≈ 350
Annual thorough examination & load testFri 9 Oct 2026, 8:00 AM · on site at Bay View Tower Emirates Lifting Inspection Services Booked 350
Weekly pre-use check1 Oct 2026 · vacuum hold 5 min, alarm, battery 88% Mohammed Rafiq · app Pass —
Battery replaced (12 V, 7 Ah)18 Jun 2026 Gulf Glazing Tools Done 260
2 vacuum pads replaced — worn edges3 Mar 2026 Gulf Glazing Tools Done 420
Annual thorough examination · proof load 500 kg16 Oct 2025 · certificate ELIS-25-10477 valid to 15 Oct 2026 Emirates Lifting Inspection Services Pass 350
First thorough examination16 Oct 2024 · certificate ELIS-24-08812 Emirates Lifting Inspection Services Pass 350
Spent on upkeep since purchase1,380

Safe use

Shown to the operator every time the QR label is scanned
HSE rules
Trained operators only
Glass handling course on the employee file
Test the vacuum hold before every lift
Gauge in the green for 1 minute
Maximum 400 kg
A 12 mm panel 2.4 × 1.25 m weighs about 90 kg
Charge it every evening
Stop lifting if the alarm sounds
Inspection booked · Fri 9 Oct, 8:00 AM
Emirates Lifting Inspection Services will test AST-TS-0012 at Bay View Tower. Mohammed Rafiq was told on WhatsApp and the reminder for 15 Oct is closed.
Problem reported · lifter out of use
Sunil Perera, Mohammed Rafiq and Arun Kumar were notified. The lifter cannot be issued until the check is signed off.