Schedule templates

Office Fit-out (Standard) Editing v3 → v4

Default template · used by 4 projects · changes apply to new projects only

Template details

Shown to project managers when they create a project
To keep v3 as it is, use “Save as new” and rename it, e.g. Office Fit-out (Fast-track).
Client visibility

Activities

11 activities12 activities + handover · durations in calendar days · rules apply when the site team updates progress
81 days to handover
#ActivityDaysDepends onResponsibleRules at update
1
2
3
4
5
6
7
8
9
10
11
12
◆
Add activity Total to handover: 81 days · longest chain 1 → 3 → 4 → 5 → 8 → 9 → 10 → 11

Preview

How a new project's schedule will look before dates are applied
To handover81 days
Own team56
Subcontractors5
LHP Metals & Glass1
Photos required11 of 1112 of 12
Activity
Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11Week 12
1Mobilization5 d
5 d
2Site protection4 d
4 d
3Demolition8 d
8 d
4MEP first fix14 d
14 d
5Gypsum & ceiling28 d
28 d
6Flooring24 d
24 d
7Glass partitions26 d
26 d
8Painting22 d
22 d
9Joinery18 d
18 d
10MEP second fix12 d
12 d
11Cleaning & snagging9 d
9 d
12Authority inspection2 d
◆Handover · day 81
Activity
Wk 1–4Wk 5–8Wk 9–12
1Mobilization
2Site protection
3Demolition
4MEP first fix
5Gypsum & ceiling
6Flooring
7Glass partitions
8Painting
9Joinery
10MEP second fix
11Cleaning & snagging
12Authority inspection
◆Handover
Own teamSubcontractorLHP Metals & GlassMilestone

Change history

Every saved version is kept
  1. v4 · draft
    Managing Partner · today
  2. v3 · split MEP into first and second fix
    Arun Kumar · 3 Aug 2026 · photos now required on every activity
  3. v2 · added site protection & screening
    Arun Kumar · 10 Feb 2026 · building management requirement
  4. v1 · created
    Managing Partner · 22 Apr 2025 · from the first office fit-out programme

Used by

4 projects · running projects keep their version
To re-plan a running project from v4, open its schedule and choose “Change template”.
Unsaved changes · v4 draft Cancel
Activity 12 added
Authority inspection runs alongside cleaning and snagging — the handover stays on day 81.