Schedule templates
Start from a template, adjust per project, then share with the client.
Standard templates
Office Fit-out (Standard)
v3 · updated 3 Aug by Arun Kumarv4 · saved just nowOffice floors of 800–1,500 m²: strip-out, MEP, gypsum, flooring, glass partitions, joinery and handover.
Preview 11 activities
- Mobilization & site setup · 5 d
- Site protection & screening · 4 d
- Demolition & strip-out · 8 d
- MEP first fix · 14 d · sub
- Gypsum partitions & ceiling · 28 d · sub
- Flooring (vinyl + carpet tiles) · 24 d
- Glass partitions & doors · 26 d · M&G glass
- Painting & finishes · 22 d · sub
- Joinery & pantry · 18 d · sub
- MEP second fix, testing & commissioning · 12 d · sub
- Cleaning, snagging & handover · 9 d
◆ Handover on day 81 · photos required on all site activities
Glass & Aluminium Installation
Partitions / shopfront · v2 · updated 12 MaySupply-and-install glass jobs: survey, shop drawings, fabrication at LHP Metals & Glass, installation and handover.
Preview 9 activities
- Site survey & measurement · 2 d
- Shop drawings & client approval · 5 d
- Fabrication at LHP Metals & Glass · 10 d · M&G
- Mobilization & protection · 1 d
- Base channels & frames · 3 d
- Glass installation · 5 d
- Doors, hardware & fittings · 2 d
- Silicone & finishing · 2 d
- Cleaning, snagging & handover · 2 d
◆ Handover after 32 working days · M&G order is raised from the PR
Retail / F&B Shop Fit-out
v2 · 20 Sep — NOC buffer 5 → 7 days after TS-26-017Mall and street shops, cafés and restaurants: landlord NOC, shopfront glass, counters and Civil Defence inspection.
Preview 13 activities
- Mall / landlord NOC & permits · 7 d
- Mobilization & hoarding · 3 d
- Demolition · 4 d
- MEP first fix · 10 d · sub
- Gypsum walls & ceilings · 12 d · sub
- Flooring · 8 d · sub
- Shopfront glass from LHP M&G · 6 d · M&G
- Joinery & counters · 10 d · sub
- Painting & finishes · 8 d · sub
- MEP second fix & T&C · 5 d · sub
- Signage & branding · 3 d · sub
- Civil Defence inspection · 2 d
- Snagging & handover · 3 d
◆ Handover · overlaps bring 81 days of work into 8–10 weeks
Your templates
Villa Glass & Showers (Short)
v1 · saved 15 Sep by Arun KumarVilla balustrades and shower enclosures with glass from LHP Metals & Glass. Made for TS-26-018.
Preview 8 activities
- Site survey & measurement · 1 d
- Shop drawings & owner approval · 3 d
- Fabrication at LHP Metals & Glass · 8 d · M&G
- Balustrade base channel · 2 d
- Balustrade glass installation · 3 d
- Shower enclosures · 3 d
- Silicone & finishing · 1 d
- Cleaning & handover · 1 d
Office Fit-out (Fast-track)
v1 · saved just now · copy of StandardFor fixed move-in dates: painting runs alongside the glass and MEP second fix alongside joinery.
Preview 11 activities
- Mobilization & site setup · 4 d
- Site protection & screening · 3 d
- Demolition & strip-out · 7 d
- MEP first fix · 12 d · sub
- Gypsum partitions & ceiling · 24 d · sub
- Flooring (vinyl + carpet tiles) · 20 d
- Glass partitions & doors · 22 d · M&G glass
- Painting & finishes · 18 d · with glass
- Joinery & pantry · 15 d · sub
- MEP second fix, testing & commissioning · 10 d · with joinery
- Cleaning, snagging & handover · 7 d
◆ Handover on day 70
Create a template
Copy a standard template or start blank. Saved templates are available to every project manager.