Viewing as Imran Sheikh · Production Supervisor. This is the phone app used on the factory floor — big buttons, works with gloves, and every tap updates the production board. Back to partner view
Friday 2 Oct · shift 7:00 AM – 4:00 PM
13 / 14 in
Good morning, Imran
Glass cut today
71%
64.2 m² of 90 m² target
Edged 118 rm Aluminium 46 bars Yield 88%
Point the camera at the QR on a job card or piece label to open it.
My queue today
Start or finish a stage — the board and the customer's order update at once
JC-26-0447-R1 Remake
NextCutting
2 shower panels, 8 mm clear → tempered
SO-MG-26-022 · Cedar Interiors · NCR-MG-26-007
MC-01 cutting table Rajan Pillai Due 2:00 PM · dispatch 5 Oct
Started 10:41 AM by Rajan Pillai on MC-01. Next stage: edging on MC-02.
JC-26-0440
AssemblyAssembly done
Sliding windows batch 2 · 14 units
SO-MG-26-019 · Blue Wave Contracting · Series 45
60%
100%
Saleem Akhtar, Joby Mathew, Kamal Hossain QC 7 Oct
Moved to QC at 10:43 AM. Ali Raza has it in his inspection list. Blue Wave's batch 2 delivery can now be booked.
JC-26-0451 LHP TS
Outsourced
Shopfront glass 12 mm · 6 pieces · 14.6 m²
SO-MG-26-021 · TS-26-017 Oasis Walk G-24
At Gulf Tempered Glass · JW-MG-26-009 Back Tue 6 Oct · QC same day
JC-26-0453 LHP TS
Planned 5 Oct
Balustrade glass 15 mm laminated · 22 rm
SO-MG-26-023 · TS-26-018 villa, Arabian Ranches 2
Sheets reserved Cut Mon 5 Oct on MC-01 Lamination at LamiGlass after tempering
Report or record
Two taps, photo optional — the partners see it in real time
Machines now
From operators' check-ins- RunningIssue 10:44MC-02 · Edging window glass
- FreeRunningMC-01 · Cutting table
- RunningMC-04 · Aluminium double saw
- RunningMC-05 · Corner crimper
MC-02 service is due Mon 5 Oct — new wheels on PR-MG-26-0030.
Today on the floor
Newest first- MC-02 issue reported
- Scrap logged · 1 piece 8 mm, 0.72 m²
- JC-26-0440 assembly completed → QC
- JC-26-0447-R1 cutting started
- JC-26-0449 cut · 28 panes 6 mm, 64.2 m²
- 46 Series 45 bars cut for JC-26-0440
- Toolbox talk: safe handling of 12 mm panels
Started — JC-26-0447-R1 cutting on MC-01
The board shows it in Cutting. Cedar Interiors' order SO-MG-26-022 stays on track for 5 Oct.Stage completed — JC-26-0440 moved to QC
14 sliding windows for Blue Wave Contracting. Ali Raza is notified for inspection.Scrap logged — 1 piece 8 mm clear, 0.72 m² (AED 38)
Booked to JC-26-0447-R1. Today's yield and the job cost are updated; QC sees the photo.