LHPMetals & Glass
6

Factory licence & compliance

Industrial licence application IND-2026-04417 · Plot 27, Al Quoz Industrial Area 4, Dubai

Step 5 of 9 Licence target Wed 28 Oct Official launch Sun 1 Nov 2026 VAT registered 1 Sep · TRN 100 7788 1234 5003
Official launch · Sunday 1 November 2026
29 days to launch

The industrial licence is the last gate. 4 steps are done, the Civil Defence inspection is next on Thu 8 Oct, and the licence is targeted for Wed 28 Oct.

5/9
4 doneStep 5 in progress4 to go
Licence steps done
4 of 9
Last: municipality approval 22 Aug
Civil Defence inspection
Thu 8 Oct
6 days · 4 of 6 checks ready6 days · 5 of 6 checks ready
Waiting on authorities
1
Environmental NOC · submitted 20 Sep
Waiting on partners
2 signatures
Metal Division Partner · MOA addendum

Licence steps

Industrial licence · Dubai · owners and documents per step
Step 5 of 9
  1. 1 · Trade name reservation
    Done 12 Jun 2026 · Managing Partner with PRO Asha Varghese
  2. 2 · Initial approval (Dubai Economy & Tourism)
    Done 30 Jun · activity: glass processing, aluminium & steel fabrication
  3. 3 · Tenancy contract & Ejari · Plot 27
    Done 15 Jul · lease to 14 Jul 2027
  4. 4 · Municipality approval (building & fit-out)
    Done 22 Aug · factory layout, mezzanine and dust extraction approved
  5. 5 · Civil Defence fire-safety In progress
    Fire-safety drawings approved · inspection Thu 8 Oct, 10:00 AM · Imran Sheikh on site, Metal Division Partner attends
    4 of 6 preparation checks are ready — evacuation plan and electrical test still open.5 of 6 preparation checks are ready — only the electrical test (booked 5 Oct) is open.
  6. 6 · Environmental NOC · dust & glass waste
    Submitted 20 Sep · with the authority · follow-up call Wed 7 Oct
  7. 7 · Partners' documents & signatures
    Pending · MOA addendum adding the Metal Division Partner and specimen signatures — he joins formally at licence issue
  8. 8
    8 · Industrial licence issued
    Target Wed 28 Oct · needs steps 5, 6 and 7 first
  9. 9
    9 · Ministry of Industry & Advanced Technology registration
    After the licence · registers the factory as an industrial establishment
  10. Official launch · Sun 1 Nov 2026
    Open to outside customers under the new licence

Civil Defence · Thu 8 Oct

Inspection preparation
4 of 65 of 6
67%
83%
  • Fire extinguishers serviced
    12 units tagged 25 Sep · valid to Mar 2027
  • Fire alarm test
    28 Sep · 18 detectors and 4 call points OK
  • Exit signs & emergency lights
    9 signs checked 28 Sep
  • Evacuation plan posted
    Draft ready · frame at 3 points + assembly sign · Imran Sheikh · due 6 Oct
  • Evacuation plan posted
    Done 2 Oct, 10:41 AM · photo attached
  • First-aid kits
    3 kits incl. glass-cut kit · checked 28 Sep
  • Electrical safety test
    Contractor booked Mon 5 Oct · Metal Division Partner

Partner documents

Metal Division Partner · joins at licence issue
  • Passport copy
    Received 18 Sep
  • Emirates ID & photo
    Received 18 Sep
  • MOA addendum signed
    Notary appointment Mon 12 Oct · all three partners
  • Specimen signatures
    At the same appointment
Reminder goes to all partners on WhatsApp on 11 Oct.

Documents vault

Licence & company documents · kept 7 years · partners only
Upload

Already in place

Ready for 1 Nov
  • VAT registration
    From 1 Sep 2026
    Done
  • Company bank account
    Emirates NBD ••7710
    Done
  • Price list & inter-company pricing
    List −8% for LHP TS · agreed 1 Sep
    Done
  • Factory team
    14 staff · shift 7:00 AM – 4:00 PM
    Done
  • Machines installed
    MC-01 to MC-09 · running
    Done

Recurring compliance

Reminders go to the owner 30 days and 7 days before each due date
ItemHow oftenLast doneNext dueOwnerStatus
Fire extinguisher service12 units · tagged by the service companyEvery 6 months25 Sep 202625 Mar 2027Imran SheikhOK
Fire alarm testDetectors, call points, soundersMonthly28 Sep 202628 Oct 2026Imran SheikhScheduled
Forklift inspection certificateMC-09 · 3 t diesel · third-party inspectorYearlyDealer certificate30 Nov 2026Nadeem AkhtarBook by 15 Nov
Waste-disposal contractGlass cullet & dust · weekly pick-upYearlySigned 1 Sep 202631 Aug 2027Grace D'SouzaOK
HSE training recordsWeekly toolbox talks · induction for new joinersWeekly2 Oct 20269 Oct 2026Imran SheikhOK
First-aid kits3 kits · refill after useMonthly28 Sep 202628 Oct 2026Imran SheikhOK
Electrical safety testPanels, earthing, machine isolatorsYearlyFirst testMon 5 Oct 2026Metal Division PartnerBooked
Industrial licence renewalStarts after the licence is issuedYearly—Oct 2027Managing PartnerAfter issue
Document uploaded
"Evacuation plan v2.pdf" is filed under step 5 · Civil Defence and the partners are told on WhatsApp.
Status sent to all three partners
Licence at step 5 of 9 · Civil Defence on Thu 8 Oct · 30 days to launch · 2 signatures still needed.
Evacuation plan marked ready
5 of 6 Civil Defence checks are done. Only the electrical test on Mon 5 Oct is left.