Factory licence & compliance
Industrial licence application IND-2026-04417 · Plot 27, Al Quoz Industrial Area 4, Dubai
Official launch · Sunday 1 November 2026
29 days to launch
The industrial licence is the last gate. 4 steps are done, the Civil Defence inspection is next on Thu 8 Oct, and the licence is targeted for Wed 28 Oct.
5/9
4 doneStep 5 in progress4 to go
Licence steps done
4 of 9
Last: municipality approval 22 Aug
Civil Defence inspection
Thu 8 Oct
6 days · 4 of 6 checks ready6 days · 5 of 6 checks ready
Waiting on authorities
1
Environmental NOC · submitted 20 Sep
Waiting on partners
2 signatures
Metal Division Partner · MOA addendum
Licence steps
Industrial licence · Dubai · owners and documents per step- 1 · Trade name reservation
- 2 · Initial approval (Dubai Economy & Tourism)
- 3 · Tenancy contract & Ejari · Plot 27
- 4 · Municipality approval (building & fit-out)
- 5 · Civil Defence fire-safety In progress4 of 6 preparation checks are ready — evacuation plan and electrical test still open.5 of 6 preparation checks are ready — only the electrical test (booked 5 Oct) is open.
- 6 · Environmental NOC · dust & glass waste
- 7 · Partners' documents & signatures
- 88 · Industrial licence issued
- 99 · Ministry of Industry & Advanced Technology registration
- Official launch · Sun 1 Nov 2026
Civil Defence · Thu 8 Oct
Inspection preparation67%
83%
- Fire extinguishers serviced
- Fire alarm test
- Exit signs & emergency lights
- Evacuation plan posted
- Evacuation plan posted
- First-aid kits
- Electrical safety test
Partner documents
Metal Division Partner · joins at licence issue- Passport copy
- Emirates ID & photo
- MOA addendum signed
- Specimen signatures
Reminder goes to all partners on WhatsApp on 11 Oct.
Documents vault
Licence & company documents · kept 7 years · partners onlyAlready in place
Ready for 1 Nov- DoneVAT registration
- DoneCompany bank account
- DonePrice list & inter-company pricing
- DoneFactory team
- DoneMachines installed
Recurring compliance
Reminders go to the owner 30 days and 7 days before each due date| Item | How often | Last done | Next due | Owner | Status |
|---|---|---|---|---|---|
| Fire extinguisher service12 units · tagged by the service company | Every 6 months | 25 Sep 2026 | 25 Mar 2027 | Imran Sheikh | OK |
| Fire alarm testDetectors, call points, sounders | Monthly | 28 Sep 2026 | 28 Oct 2026 | Imran Sheikh | Scheduled |
| Forklift inspection certificateMC-09 · 3 t diesel · third-party inspector | Yearly | Dealer certificate | 30 Nov 2026 | Nadeem Akhtar | Book by 15 Nov |
| Waste-disposal contractGlass cullet & dust · weekly pick-up | Yearly | Signed 1 Sep 2026 | 31 Aug 2027 | Grace D'Souza | OK |
| HSE training recordsWeekly toolbox talks · induction for new joiners | Weekly | 2 Oct 2026 | 9 Oct 2026 | Imran Sheikh | OK |
| First-aid kits3 kits · refill after use | Monthly | 28 Sep 2026 | 28 Oct 2026 | Imran Sheikh | OK |
| Electrical safety testPanels, earthing, machine isolators | Yearly | First test | Mon 5 Oct 2026 | Metal Division Partner | Booked |
| Industrial licence renewalStarts after the licence is issued | Yearly | — | Oct 2027 | Managing Partner | After issue |
Document uploaded
"Evacuation plan v2.pdf" is filed under step 5 · Civil Defence and the partners are told on WhatsApp.